HomeMy WebLinkAboutAspro, Inc. CO#1 - 6/25/2018 CHANGE ORDER NO. 1
Owner Waterloo Regional Airport,City of Waterloo Iowa Date June 15,2018
Project Runway 12/30 Pavement Joint Repair and Pavement Marking
Owner's Contract No. FAA AIP Project No. 3-19-0094-045 Contractor Aspro,Inc.
Date of Contract Start May 21,2018
You are directed to make the following changes in the Contract Documents. Description:
ADD ALTERNATE BID NO.1
1 RUNWAY AND TAXIWAY SF (35,200) $0.75 $ (26,400.00)
MARKING-RUNWAY 12/30
REFLECTIVE MEDIA(TYPE I,
2 GRADATION A)-RUNWAY 12- LB (2,800) $0.55 $ (1,540.00)
30
101 RUNWAY AND TAXIWAY SF 135,800 $0.65 $ 88,270.00
MARKING-RUNWAY 12/30
102 TAXIWAY REFLECTIVE MEDIA LB 8,100 $0.50 $ 4,050.00
(TYPE I,GRADATION A)
TOTAL
CHANGE
ORDER $ 64 380.00
Reason for Change Order:
The purpose of this change order is to remark the entire Runway 12/30. The project originally only included
areas not previously marked in the last 4 year period. The new runway marking is significantly more visible than
what was originally intended to remain in place. This change order will allow for consistent visibility and
reflectivity of the Runway 12/30 markings.
Because of the increased pavement marking quantities,the contractor has indicated that he will honor the unit
price in their contract for Runway 18/36 for the Runway 12/30 markings.
Runway 12/30 Joint Repair and CO-1 Project No—60550592
Airfield Pavement Marking
1
CONTRACT PRICE CONTRACT TIMES(Calendar Days)
To substantial To final
completion completion
Original: $ 575,859.35 Original: 90
Previous C.O.s(DEDUCT):$ 0.00 Previous C.O.s(ADD): 0
This C.O. (ADD): $ 64,380.00 This C.O. (ADD): 0
Contract Price with all REVISED: 90
approved Change Orders: $ 640,239.35
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s)ordered herein,including all impact,delays,and acceleration costs. Other than the dollar amount and time
allowance listed above,there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED: i
By: Ll�l s .,�, J►�a / r
Engineer(Authorized Signature) Date
APPR rr
By:
Owner(Authorized Si ture) Date
ACC TE[f)
Ey:—AW
Contractor(Authorized Signature) Date
Runway 12/30 Joint Repair and CO-1 Project No–60550592