HomeMy WebLinkAboutAECOM - CO#2 Flow Equalization Facility Overflow Cont 880 - 812/19AECOM July 31, 2019 Mr. Randy Bennett Waste Management Services 3505 Easton Avenue Waterloo, Iowa 50702 AECOM 501 Sycamore Street Suite 222 Waterloo, Iowa 50703 www.aecom.com Subject: Change Order No. 2 Flow Equalization Facility Overflow Connection to Satellite WPCF Waterloo, Iowa City Contract No. 880 AECOM #60507078 Dear Mr. Bennett: 319-232-6531 tel 319-232-0271 fax Enclosed please find Change Order No. 2 for the above -referenced project. The purpose of this change order is to power and control sump pumps in the metering manhole and the control valve manhole from the Blower Building at the Satellite Plant and via SCADA system. The contract documents called for a control cabinet that would no longer be required as controls would be routed to the Blower Building. It is recommended to move forward with this Change Order No. 2 in the amount of $10,078.83. If you have any questions or need additional information, please let us know. Thank you. Yours sincerely, Ross A. Hillsman, PE Enclosure: As Noted c: Boomerang Corporation P:\605070781600_Construction_Support\670_Change-Orders12019-7-31 Tmsmtl to Randy Bennett Watedoo FEQ Overflow - CO #2.docx CHANGE ORDER NO. 2 Owner: City of Waterloo, Iowa Date: July 31, 2019 Project: Flow Equalization Facility Overflow Connection to Satellite WPCF Owner's Contract No.: City Contract No. 880 Contractor: Boomerang Corporation Date of Contract Start: November 27, 2017 $ Original Contract: $693,700 You are directed to make the following changes in the Contract Documents. Description: Add new conduit and wiring to run and control the sump pumps from the blower building in lieu of controlling them via local control cabinet. Deduct the costs for the control cabinet as originally indicated in the contract documents. Addition for Conduit and Wiring $11,328.83 Deduct for Control Cabinet $( 1,250.00) NET ADD $10,078.83 Reason for Change Order: The purpose of the change is to power and control the sump pumps in the metering manhole and the control valve manhole from the Blower Building at the Satellite Plant and via SCADA system. The contract documents called for a control cabinet that would no longer be required as controls would be routed to the Blower Building. A deduct is included for the cabinet. CONTRACT PRICE Original: $ 693,700.00 Previous C.O.s (ADD/DEDUCT): $ 39,237.42 This C.O. (ADD/DEDUCT): $ 10,078.83 Contract Price With All Approved Change Orders: Original: Previous C.O.s (ADD/DEDUCT): This C.O. (ADD/DEDUCT): $ 743,016.25 REVISED: Original Completion Date: Revised Completion Date: CONTRACT TIMES (Calendar Days) To Substantial To Final Completion Completion May 31, 2018 To Be Determined It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO APPROVED lj City of Waterloo (Authorized Signature) By: ACCEPTED: By: oomerang Corporation (Authorized Signature) P:`605070781600_Construction_Support\670_Change-Orders12019-07-31 -CO2-FSQ (002).docPage 1 of 1 /f 1 Date: Date: AECOM 60507078 2 Project No. Change Order No.