October 1, 2019
Mr. Randy Bennett
Waste Management Services
3505 Easton Avenue
Waterloo, Iowa 50702
Subject: Change Order No. 4
Satellite Wet Well Rehabilitation
Waterloo, Iowa
City Contract No. 907
AECOM #60488465
Dear Mr. Bennett:
AECOM
501 Sycamore Street
Suite 222
Waterloo, Iowa 50703
www.aecom.com
319-232-6531 tel
319-232-0271 fax
Enclosed please find Change Order No. 4 for the above -referenced project. The purpose of this change order is
that during work on the Anerobic Lagoon Wet Well, it was discovered the floor of the wet well was coated with
epoxy. This needed to be removed for the new Sprayroq product to be installed on the surfaces of the wet well.
The pipes and pump bases were found to be corroded during construction activities. It was decided to coat these
with Sprayroq to protect them long term. The contractor was able to leave the gates in-place during coating
activities (a deduct was included with this activity). Additional bypass pumping was also required for the additional
work performed.
It is recommended to move forward with this Change Order No. 4 in the amount of $19,505.00. If you have any
questions or need additional information, please let us know. Thank you.
Yours sincerely,
Ross A. Hillsman, PE
Enclosure: As Noted
c: WRH, Inc.
P:1604864651600_Construction_Suppor11670_Change-Orders12019-10-1 CO #4 - Tmsmtl to Randy Bennett Waterloo Satellite Wet Well Rehab.docx
CHANGE ORDER NO.4
Owner: City of Waterloo Date: October 1, 2019
Project: Satellite Wet Well Rehabilitation
Owner's Contract No.: 907 Contractor: WRH, Inc.
Date of Contract Start: $ Original Contract: $1,839,380.00
You are directed to make the following changes in the Contract Documents. Description:
Add for removal of epoxy grout on floor of Anaerobic Lagoon Wet Well. Add for blasting and coating of piping and pump bases with
Sprayroq product. Provide a deduct for leaving gates in place. Add for additional bypass pumping associated with the additional
work.
NET ADD $19,505.00
Reason for Change Order:
During work on the Anerobic Lagoon Wet Well, it was discovered that the floor of the wet well was coated with epoxy. This needed to
be removed for the new Sprayroq product to be installed on the surfaces of the wet well. The pipes and pump bases were found to
be corroded during construction activities. It was decided to coat these with Sprayroq to protect them long term. Contractor was able
to leave the gates in-place during coating activities (a deduct was included with this activity). Additional bypass pumping was
required for the additional work performed.
CONTRACT PRICE
Original: $ 1,839,380.00 Original:
Previous C.O.s (ADD/DEDUCT): $ 73,948.00 Previous C.O.s (ADD/DEDUCT):
This C.O. (ADD/DT): $ 19,505.00 This G.O. (ADD/DEDUCT):
Contract Price With All Approved
Change Orders: $ 1,932,833.00 REVISED:
CONTRACT TIMES (Calendar Days)
To Substantial To Final
Completion Completion
3
Original Completion Date: October 1,
2019
Revised Completion Date:
To be
Determined
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including
all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar
compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
APPROVED:
By:
City of Waterloo (Authorize
ACCEPTED:
By:
ignature) Date:
g4 -iltcf. PACT/06:04-
I uthorized
, , .4-
lnt'TAuthorized Signature) Date:
Page t of 1
Pa60488465\600Construction_Supportl670_C6ange-Orders52019-10-1-COk4 - Satellite Wet Well - WRadoc
t°ltltr'1
AECOM
60488465 4
Project No. Change Order No.