HomeMy WebLinkAboutWoodruff Construction, LLC - C.O. #5 - #7 - 10/7/2019CHANGE ORDER
® Mark Kuiper, RITLAND+KUIPER
❑ Nate Goetsch, Woodruff Construction
❑ Quentin Hart, Mayor of Waterloo, Iowa
0
PROJECT: Lincoln Park
OWNER: City of Waterloo, Iowa
F.Y. 2019 #973
TO: Nate Geotsch
Woodruff Construction
1717 Falls Avenue
Waterloo, IA 5070I
CO No.: 05
DATE OF ISSUANCE: 09/11/2019
FROM:
RITLAND+KUIPER Landscape Architects
501 Sycamore Street, Mezzanine A
Waterloo, Iowa 50703
You are directed to make the following changes in this Contract:
1. Contractor reimbursement for removal and disposal of fountain basin in Lincoln Park.
TOTAL INCREASE TO CONTRACT
Attachments: 2019.09.06 Estimate from Woodruff Construction
$3,650.00
Not valid until signed by both the Owner and Architect.
Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract sum or Contract time.
The original Contract Sum was $734,330.30
$169,250.00
$903,580.30
$3,650.00
$907,230.30
zero ( 0 ) Days
Net change by previously authorized Change Orders
The Contract Sum prior to this Change Order was
The Contract Sum will be (increased) by this Change Order
The new Contract Sum including this Change Order and Change Order #01 & #02 will be
The Contract Time will be (unchanged)
RITLAND+KUIPER
Landscape Architects Woodruff Construction City of Waterloo
ARCHITECT CONTRACTOR
OWNER
//741
Signatur Signature Signature
Mark Kuiper, ASLA, LEED AP Nate Goetsch Mayor Quentin Hart
CHANGE ORDER
® Mark Kuiper, RITLAND+KUIPER
❑ Nate Goetsch, Woodruff Construction
❑ Quentin Hart, Mayor of Waterloo, Iowa
0
0
0
PROJECT: Lincoln Park
OWNER: City of Waterloo, Iowa
F.Y. 2019 #973
TO: Nate Geotsch
Woodruff Construction
1717 Falls Avenue
Waterloo, IA 50701
CO No.: 06
DATE OF ISSUANCE: 09/19/2019
FROM:
RITLAND+KUIPER Landscape Architects
501 Sycamore Street, Mezzanine A
Waterloo, Iowa 50703
You are directed to make the following changes in this Contract:
1. Deduction of 288 SF of porous pavement
2. Deduction of 180 SF of PCC pavement, 6"
3. Installation of 3 Thornless Honeylocust `Skyline' 2" caliper trees, B & B and planting soil as per plan note
13.
4. Installation of 360 SF of shredded hardwood mulch as per plan note 5.
TOTAL DEDUCT TO CONTRACT
Attachments: 2019.09.17 Estimate from Woodruff Construction
($294.27)
Not valid until signed by both the Owner and Architect.
Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract sum or Contract time.
The original Contract Sum was ... $734,330.30
Net change by previously authorized Change Orders $169,250.00
The Contract Sum prior to this Change Order was $903,580.30
The Contract Sum will be (decreased) by this Change Order ($294.27)
The new Contract Sung including this Change will be $903,286.03
The Contract Time will be (unchanged) zero ( 0 ) Days
RITLAND+KUIPER
Landscape Architects
ARCHITECT
Signatu
Mark Kuiper, ASLA, LEED AP
Woodruff Construction
CONTRACTOR
Sig rature
Nate Goetsch
City of Waterloo
OWNER
Signature
Mayor Quentin Hart
CHANGE ORDER
® Mark Kuiper, RITLAND+KUIPER
❑ Nate Goetsch, Woodruff Construction
❑ Quentin Hart, Mayor of Waterloo, Iowa
0
0
PROJECT: Lincoln Park
OWNER: City of Waterloo, Iowa
F.Y. 2019 #973
TO: Nate Geotsch
Woodruff Construction
1717 Falls Avenue
Waterloo, IA 50701
CO No.: 07
DATE OF ISSUANCE: 09/25/2019
FROM:
RITLAND+KUIPER Landscape Architects
501 Sycamore Street, Mezzanine A
Waterloo, Iowa 50703
You are directed to make the following changes in this Contract:
I. In an effort to protect as many subsurface tree roots as possible, the City has asked that all concrete
pavements (colored and plain) be installed with 6" of concrete (with steel reinforcement as per the
construction documents) but that all modified subbase not be installed to keep excavation as minimal as
possible.
Some excavation has taken place beyond the 6" depth required for pavement already. In those areas, the
Contractor shall use modified subbase (compacted as per the specifications) to reach the required
subgrade depth for installation of the 6" pavement. All other areas shall be excavated to the 6" depth for
pavement installed in-situ soils (some rolling and compaction may be necessary for these soils to
provide adequate bearing for the pavements).
Please provide quantities and price adjustments for the decreased soil excavation and decreased
modified subbase required to accommodate this change.
TOTAL (DEDUCT) TO CONTRACT ($5,719.00)
Attachments: 2019.09.25 Estimate from Woodruff Construction
Not valid until signed by both the Owner and Architect.
Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract sum or Contract time.
The original Contract Sum was $734,330.30
Net change by previously authorized Change Orders $169,250.00
The Contract Sum prior to this Change Order was $903,580.30
The Contract Sum will be (decreased) by this Change Order ($5,719.00)
The new Contract Sum including this Change Order will be $897,861.30
The Contract Time will be (unchanged) zero ( 0 ) Days
RITLAND+KUIPER
Landscape Architects Woodruff Construction
ARCHITECT
Mark Kuiper, ASLA, LEED AP
CONTRACTOR
Signature
Nate Goetsch
City of Waterloo
OWNER
Signature
Mayor Quentin Hart