HomeMy WebLinkAboutJ.F. Brennan Co. - CO#2 - FY2020 Cedar River Bladder Dam Repairs - 1/27/2020CHANGE ORDER NO. 2
Owner City of Waterloo Date: January 16, 2020
Project FY 2020 Cedar River Bladder Dam Repairs
Owner's Contract No. 996 Contractor: J.F. Brennan Company, Inc.
Date of Contact Start November 18, 2019 Contract Amount: $ 388,350.00
You are directed to make the following changes in the Contract Documents. Description:
2-1 DELETE COFFERDAM PUMPING
2-2 DELETE BID ITEM 13 (CONCRETE GROUT)
2-3 DAM ACCESS
2-4 ADD BAY 1 AND 2 INSPECTION
2-5 BID BOND CREDIT
TOTAL ADDITIONS
$ (100,000.00)
$ (26,000.00)
$ 10,000.00
$ 25,000.00
$ (2,000.00)
$ (93,000.00)
Reason for Change Order
2-1 to 2-3 After completion of dive Inspection, It was determined the cofferdam pumping would not be required, no concrete
grout would be required, and access to the dam would be provided without the cofferdam.
2-4 The contractor offered a change order price to complete inspection of Bays 1 and 2 while he was on -site, resulting
in a significant cost -savings to the city, and an opportunity to inspect the remaining portions of the dam
2-5 Due to project scheduling, the contractor never provided bid bond for the project. Since the project was completed without
this bond, the contractor provided a credit to the project.
CONTRACT PRICE
Original:
Previous C.O.s (ADD/DEDUCT)
This C.O. (ADD/DEDUCT)
Contract Price with all approved
Change Orders:
To Final
Completion
$ 388,350.00 Original Completion Date: 1/15/20201 1/31/2020
$ (75,080.00)
$ (93,000.00) Revised Completion Date: 1/15/20201 1/31/2020
$ 220,270.00
CONTRACT TIME
To Substantial
Completion
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND CONVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPROVED: n ��
BY: E (..elY1�w
Owner (Authorized Signa ure)
ACCEPTED:
BY:
Cof(tractor (Authorized Signature)
ACCEPTED:
BY:
AECOM
Date
f/2,1/WIZ'
Date
01/22/2020
Date
AECOM
606129641
2
Project No. C.O. No.