HomeMy WebLinkAboutWRH, Inc. - CO #8 - Contract No. 907 - 2/10/2020Owner. City of Waterloo
Project'. Satellite Wet Well Rehabilitation
Owners Contract No. 907
Date of Contract Stan
CHANGE ORDER NO. 8
Date February 4, 2020
Contractor' WRH, Inc.
S Onginal Contract: $1 839,380.00
You are directed to make the following changes in the Contract Documents. Description.
Additions:
• Construction of sanitary sewer piping and associated structures which will create a crossover connection between domestic and industrial interceptor sewers
the east ode of the Cedar River
Cross -Over Connection Addition = 5659,500.00
Deductions: progressed, it was determined that this work was not needed
•. Bid item No 4 - Anaerobic Grout As construction of the project
Anaerobic Grout Deduction = 586,000.00
• Bid Item No. 5 - Anaerobic Repair As Construction of the project progressed. it was determined that only a part amount of this wok was needed.
Anaerobic Repair Deduction = 578,400.00
• Bid item No 9 - Satellite Bypass The construction of the cross -over connection between the domestic and industrial Interceptors on the east side of the Cedar
River will negate the need for this temporary bypassing bid item.
Satellite Bypass Deduction = 5200,000.00
• Bid Item No. 21 - Sludge Grout As Construction of the project progressed, it was determined that this work was not needed.
Sludge Grout Deduction = 525,000.00
• Bid Item No. 22 - Sludoe Repair As construction of the project progressedit was determined that only a partial amount of this work was needed.
Sludge Repair Deduction = S23,800.00
TOTAL ADDITIONS: $659,500.00
TOTAL DEDUCTIONS: ( 5393,200.00j
NET CHANGE ORDER AMOUNT: $266,300.00
Reason for Change Order
This change order will improve the constructability of the Satellite Wet Well Rehabilitation Project by eliminating uncertainties associated with installation
of a temporary industrial wastewater bypassing system. The initial capital investment for the cross -over piping and structures on the east side of the
Cedar River is projected offset by savings on te thesystemer eed forr a tempo arynbypasseed rsystempsh uldorary ypass
system (e.g., the Gatewell li Rea habilitation Project) This cross -over system will also eliminate
repairs/rehabilitation of the pipes under the Cedar River be required.
CONTRACT PRICE
Original.
S 1,839,380.00 Onginal,
Previous C.O.s (AD018EUUGTi. S 123,245.00 Previous C.O.s (ADD/6E000TT)-
This C.O. (ADDAX -MUG -Ft S 2(56,300 00 This C.O. (ADDIDEDUCT).
Contract Price With All Approved
Change Orders: $ 2,228,925.00 REVISED.
Original Completion Date
Revised Completion Date
CONTRACT TIMES (Calendar Days)
To Substantial To Final
Completion Completion
4
October 1. 2019
To be Determined
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the changets) ordered herein. including all impact, delays.
and acceleration costs. Other than the dolor amount and time allowance listed abovethere shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
APPROVE
By: 111
lA
City al Waterloo tAvVonzed Sigratwe)
ACCEPTED:
By
(AUhonzed 9pnaa+re)
Date
Dale
Page I of 1
P'18d4884651600_CantnxUan_SupporPa7o_Change-Orders\2d20-02-04 - CO#8 - Sateiote Wetwall - WRH doc
Z-164lu-zv
AECOM
60488465 8
Project No Change Order No
AECOM
February 4, 2020
Mr. Randy Bennett
Waste Management Services
3505 Easton Avenue
Waterloo, Iowa 50702
Subject: Change Order No. 8
Satellite Wet Well Rehabilitation
Waterloo, Iowa
City Contract No. 907
AECOM #60488465
AECOM
501 Sycamore Street
Suite 222
Waterloo, Iowa 50703
www.aecom.com
319-232-6531 tel
319-232-0271 fax
Dear Mr. Bennett.
Enclosed please find Change Order No. 8 for the above -referenced project. This change order includes the
following:
Additions:
• Additional construction of sanitary sewer piping and associated structures which will create a cross -over
connection between the domestic and industrial interceptor sewers on the east side of the Cedar River near
Lafayette Street.
Deductions:
• Anaerobic Grout Work Item Elimination
• Anaerobic Repair Work Item Quantity Reduction
• Satellite Bypass Work Item Elimination
• Sludge Grout Work Item Elimination
• Sludge Repair Work Item Quantity Reduction
It is recommended to move forward with this Change Order No. 8 in the net amount of $266,300.00. If you have
any questions or need additional information, please let us know. Thank you.
Yours sincerely,
Ross A. Hillsman, PE
Enclosure: As Noted
c: WRH, Inc.
P160488465\600_Construction Support\670_Change-Orders\2020.01-29 CO *8 - Tmsmtl to Randy Bennett Waterloo Satellite Wet Well
Rehab.docx
WRH, Inc.
November 25, 2019
AECOM (#60488465)
501 Sycamore Street, Suite 222
Waterloo, IA 80704
Satellite Wet Well Rehabilitation Contract No. 907
Re: WRH CAR 06: Satellite Cross -Over Structure
Attn: Ross Hillsman
WRH, Inc. is pleased to provide this proposal for the installation of the Satellite Wet
Well Cross -Over Structures based on drawings dated October 2019.
General Conditions $34,500
• Mobilization
• Temporary Site Facilities
• Temporary Utilities
Civil & Site Work $197,000
• Clear & grub the work area
• Sheeted/Coffered excavation (assumed 40' x 20' at 20' +/- depth)
• Dewatering wells installed outside of sheeted excavation to bedrock. Sump
dewatering will be performed inside the excavation.
• Backfill and sheeting removal following installation of structures
• Seeding & surface restoration
Installation of Manhole Structures $393,000
• New 96" ID FRP Manholes
• Flat top with integrated manhole cover
• CIP Concrete Base and Top Slabs
• New Plasti-Fab fiberglass gates: (1) 36" & (2) 42" gate
Site Pipe Installation $35,000
• New 42" and 36" PVC pipe spools from precast structures
• New fernco-style boot connections between new spools and existing pipe
• Concrete collars at PVC -RCP connections
• New 42" PVC Cross -Over pipe between structures
Proposal: $659,500
WRH, Inc. • PO Box 256, Amana, Iowa 52203 • 1648 T Avenue South Amana, IA 52203
Office: 319-622-3816 • Fax: 319-622-6095 • www.wncconstruction.com • info@wendlerinc.com
This proposal does not include:
• Survey control / staking (provided by AECOM)
• Potholing / confirmation of pipe depth prior to ordering structures
• Easements / Landowner coordination of any kind
• Temporary bypass pumping at upstream manholes or lagoon for installation of
structures (to be provided by the City)
• Secondary pumping or storage provisions of waste water (to be provided by the
City)
Regards,
Todd Weiss - Project Manager
WRH, Inc.
WRH, Inc.