HomeMy WebLinkAboutLodge Construction - CO#1 - FY19 Yard Waste Water and Sanitary Sewer, Cont 952 - 6/10/2010CITY OF WATERLOO, IOWA
CHANGE or EXTRA WORK ORDER NO, 1
PROJECT: P,Y, 2019 YARD WASTE WATER AND SANITARY SEWER EXTENSION, CONTRACT NO, 952
Date Prepared, March 05, 2019 AMOUNT: $ 12,868,24 Increase
TO; Lodge Construction, Inc, Contractor
You are hereby ordered to make the following changes from the plans and specifications or
perform the following extra work on your contract dated September 4, 2018,
A, Description of change to be made or extra work to be done:
1, (#8001) Provide and install "crusher run" aggregate to the rocked yard area,
2, (#8002) Provide and install "3"-9" clean road stone aggregate to the rocked yard area,
3. (#8003) Provide and install "3/4" and 1" road stone aggregate to the rocked yard area,
B. Reason for ordering change or extra work:
1.. 3. Needed to restore disturbed areas of rocked yard area.
C. Settlement for cost of work to be made as follows:
1, (#8001) Unit price of $17.00/ton x 325,50 ton = $5,533,50
2, (#8002) Unit price of $26,50/ ton x 163,27 ton = $4,326,66
3, (#8003) Unit price of $19,00/ ton x 158,32 ton = $3,008,08
CITY OF WATERLOO
BY; Y15= c0—°/I�
Quentin Hart, Mayor Date
ATTEST:
BY:
Kelley, Felchle, •T, Clerk Date
PUBLIC WORKS
Total Net Increase $ 12,868,24
LODGE CONSTR CTION, INC. (CONTRACTOR)
BY: u`crj,A, 9
Date
LOL
TITLE:
PRINTED NAME:
WAYNE OLAASSEN ENGINEERING &
SURVEY G,,NCt
By; By:
Randy Bennett Date William J. Claassen, PE Date
(File: My Documents/Change Order/MASTER)
Item Coversheet
Page 1 of 1
CITY OF WATERLOO
Council Communication
Motion approving change order No. 1 for a net increase of $12,868.24 in conjunction with the FY2019 Yard Waste Water and Sanitary
Sewer Extension Contract No. 952 for the City of Waterloo Yard Waste Site, and authorize the Mayor and City Clerk to execute said
document.
City Council Meeting: 6/10/2019
Prepared: 6/6/2019
SUBJECT:
Submitted by:
Recommended Action:
Summary Statement:
Expenditure Required:
Source of Funds:
Policy Issue:
Motion approving change order No. 1 for a net increase of $12,868.24 in conjunction with the
FY2019 Yard Waste Water and Sanitary Sewer Extension Contract No. 952 for the City of
Waterloo Yard Waste Site, and authorize the Mayor and City Clerk to execute said
document.
Submitted By:Randy Bennett, Public Works Manager
Approve Change Order
Additional crusher run, clean road stone and road stone aggregates to restore disturbed
areas of the rocked yard area.
$12,868.24