HomeMy WebLinkAboutAspro, Inc.-12/7/2015CITY OF WATERLOO Council Communication Motion approving Change Order No. 2 for a net decrease of $45,776.45 for the F.Y. 2015 Asphalt Overlay Program, Contract No. 874; and authorize the Mayor and City Clerk to execute said document. City Council Meeting: 12/7/2015 Prepared: 12/1/2015 REVIEWERS: Department Reviewer Action Date Engineering 'Thorson, Eric Approved 12/2/2015 - 10:09 AM Motion approving Change Order No. 2 for a net decrease of $45,776.45 SUBJECT: for the F.Y. 2015 Asphalt Overlay Program, Contract No 874: and authorize the Mayor and City Clerk to execute said document. Submitted by: Submitted By: Jamie Knutson, PE, Associate Engineer This is the accumulated amount of adjustments from original to final Summary Statement: quantities that were determined necessary during the construction of the project, which results in a decrease to the total project cost. Source of Funds: Local Option Sales Tax CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 2 PROJECT: F.Y. 2015 ASPHALT OVERLAY PROGRAM , CONTRACT NO. 874 Date Prepared: April 28, 2015 AMOUNT: $ 45,776.45 Decrease TO: Aspro, Inc. , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated February 17, 2014. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction. B. Reason for ordering change or extra work: As -built quantities varied for some bid items. C. Settlement for cost of work to be made as follows: Compensation already made to contractor through original bid items. See attached summary. Total Net Decrease $ 45,776.45 CITY O ATERLOO 1 BY: '17/, � 7/, Mayor Date EST: �a s City Clerk a e Aspro. Inc. CONTRACTOR BY: 4%li'7�1ti� //h o%S Date PRINTED NAME: /n/t 7 - TITLE: TITLE: rf �Df�✓� APPROVED: E'. 2015. ASPHALT OVERLAY PROGRAM CONTRACT #874 _ FINAL QUANTITY SUMMARY ASPRO ORIGINAL FINAL QUANTITY _BID ITEM DESCRIPTION - UNIT, UNIT PRICE QUANTITY Ou ITY DIFFERENCE INCR/DECR _ I REMOVED AND REPLACE WITHE-1 INLET EACH $ 3,595.00 1.00 1.00 § 2 REMOVE AND REPLACE E-1-C (USE EXISTING CASTING) EACH $ 3,095.00 5.00 13.00 8.00 $ 24,760.00 3 REMOVE AND REPLACE E-2-C(USE EXISTING CASTING) EACH $ 4,500.00 3.00 4.00 1.00 $ 4,500.00 4 REMOVE AND REPLACE INTAKEBOXOUT/E-1-C EAOH S 1 595.00 mool 9.00 (9.00) § 14,355.00 5 _ _ REMOVE AND REPLACE INTAKE BOXOUT/E-2-C EACH 1 $ 2,490.00 9.00 8.00 1.00 $ 2,490.00) 6 FURNISH E-I -C INLET CASTING EACH $ 875.00 3.00 1,00 2.00 $ 1,750.00 7 FURNISIl E-2-C INLET CASTING EACH 1,850.00 1.00 3.00 2.00 $ 3,7.00.00 9 REMOVE STRUCTURE EACH _$__ $ 2,665.00 1.00_ 1.00 $ 9 REM/REPRA INLET TOP EACH $ 2880.00 _ 1.00 1.00 S 10 REMOVE AND REPLACE, MH BOXOUT _ EACH $ 1,525.00 _ 44.00_ 30.00 14.00 $__(2%350k0) 11 STORM SEWER, 10" TRUSS _ LF $ 95.00 5.00 86.00 81.00 $ 7,695.00 _ 12 REMOVE AND REPLACE SAVOR D/W, 6" PCC SY $ 65.50 100.70 199.60 98.90 $ 6_,477.95_ 13 REMOVE SIDEWALK SY $ 9.90 980.40 986.00 5.60 _ $ _ 55.44 14 _ _ SIDEWALK, 4"YCC _ $ 26.05 465.70 457.00 (8.70) $ (226.64) 15 SIDEWALK, 6" PCC -SY-- SY $ 52.65 604.30 606.00 1.70 $ 89.51 16 _ SIDEWALK CURB SECTION LF -sF--1 $ 14.00 72.00 166.70 94.70 $ 1,325.80 17 PEDESTRIAN RAMP DETECTABLE WARNING SURFACE $ 31.00_ 937.00 848.00 89.00) $ (2,759.00 18 TOPSOIL REMOVAL FROM PARKING SY Is 11.40 378.70 189.10 (189.20) $ (2,156.88 19 TOPSOIL SY $ 25.00 4.80 12.20 7.40 $ 185.00 20 REMOVE AND REPLACE 24" C & G/6" PCC LF I $ 7A.00 102.00 294.70 192.70 S 4,624.80 21 _ REMOVE AND REPLACE 24" C&G/9" PCC $ 27.00 293.00 259.70 33.30) $ 5899.10 22 REMOVE PAVING $ 12.00 _ 311.10 311.10 $ 23 6" FCC PAVING $ 53.00 311.10 311.10 $ 24 CLASS 10 EXCAVATION $ 4.00 1 11.10 111.10 $ 25 FULL DEPTH PATCH, REM/REP 6" PCC FEA $ 63.00 37.30 19.70 (13.60 $ 856.80 26 RECYCLED ASPHALT _ $ 65.00 77.20 103.70 26.50_ $ 1,722.50 27 _ PAVEMENT SCARIFICATION _ $ 6.45 40,582.70 40,756.00 1,117.78 28 MII L WEDGE $ 2,200.00 _ _ 77.00 76.00 1.00 $ 2,200.00] 29 CRACKANDSEAT $ 2.47 39,425.90 39,425.90 $ 30 SURFACE PATCH $ 237.00 52.00 26.47 25.53 $ 6,050.61 31 HMA 1,000,000 ESAL) INTERMEDIATE„ 3/4" MIX, 60% CR _ TON $ 111.15 4,58L00 4,683.63 102.63 $ 11,407.32 32 HMA 1,000,000 ESAL SURFACE, 1/2" MIX, NO FRICTION REQD., 60% CR. TON $ 112.30 5,082.10 5,217.02 134.92 $ 15,151.52 33 HMA INTERLAYER TON $ 149.30 1,001.50 1,019.26 17.76 $ 2,651.57 34. HMA3,000,000 ESAL INTERMEDIATE, 3/4" MIX, 75% CR _TON $ 111.35 3,776.90 3,129.17 647.73 $ 72,124.74 35 HMA (3,000,000 ESAL) SURFACE 1/2" MLX, NO FRICTION REQD., 75% CR TON $ 116.10 7,398.40 7,402.01 3.61 $_ 419.12 36 PAVEMENT SAMPLES AND TESTING LS $ 9,750.00 1.00 0.92 0.08 _$8(09.25) - 37 _ INLET UMAR EACH $ _200.00 66.00 48.00 (18.00 $ _ 3,6( 00.00) (3,295.00) 38 H UNIVERSAL MADJ. RING OR EQUAL EACH $ 615.00 78.00 45.00 (33.00 $ 39 UMARED CONCRETE ADJUSTMENT EACH $ 1,045.00 19.00 20.00 1.00 $ 1,045.00 40 FURNISH M INSTALL MANHOLE CASTING _ EACH $ 890.00 1.00 5.00 4.00 $ 3,560.00 41 PAVEMENT SYMBOLS EACH $ MARI 13.00 15.00_ 2.00 $ 570.00 42 PAINTED PAVEMENT MARKINGS STA $ 47.00 _ 179.92 256.17 76.25 $ 3,593.75 43 TRAFFIC CONTROL__ LS $ 141100.00 1.00 1.0000 $ 1001 WHISTLEIRODENT GUARDEACH $ 137.50 10.00 _ 23.00 13.0000 $ 1,787.50 1002 FULL DEPTH PATCH HMA 'TON $ 237.00 12.00 53.00 41.0000 $ 9,717.00 _ INCREASE/DECREASE $ 45,776.45 PAY ESTIMATE #1 $ 8,057.43 PAY ESTIMATE 112 _ _ $ 48,916.31' PAY ESTIMATE 43 May 14,2015 $ 485,192.73 Aspro Date _ PAY ESTIMATE #4 May 28, 2015 $ 161,931.80 PAYESTIMATE#5 Jaac 11,_ 2015 $ 811,428.78 PAY ESTIMATE 46 _ _ S 442,471.1_6 >O PAY ESTIMATE #7 $ 471,058. of Waterloo Date. PAY ES'T'IMATE #8 Ad) 30, 2015 $ 242,100.86 PAY ESTIMATE #9 August 13, 20_15 $ 109,826.8 PAY ESTIMATE #10 September 2, 2015 _ _ -S-286,28r79 PAY ESTIMATE #11 Se [ember 25, 2015 _ $ 95,378.88 _ PAY ESTIMATE #12 October 15, 2015 $ 59,111.48 PAY ESTIMATE #13 October 30, 2015 _ $ 127,097.69 PAY ESTIMATE # 14 November 12, 2015 $ 21,202.93 RETAINAGE _ _ $ 177,366.51_ TOTAL PAYMENT $ 3,547,330.27 ORIGINAL CONTRACT AMOUNT $ 3,588,88_7.72 _ CHANGE ORDER #I SIGNED BY CITY ENGINEER _ $ 4.,219.00 FINAL QUANTITY ADJUSTMENT $ 45,776.45) FINAL CONTRACT AMOUNT' $ 3,547,330.27