HomeMy WebLinkAboutPeters Construction - CO #2 - 5 Bros Exhibition Hall Ceiling Renovation - 7.13.20PETERS
CONSTRUCTION CORPORATION
To: I & S Group, Inc.
115 E Hickory Street
Suite 300
Mankato, MN 56001
Ph: 507-387-6651
Number: 5
Date: 7/6/20
Job: 20-044 Five Sullivan Brothers Ceiling
Phone:
Description: Added Costs and Substantial Completion Extension for Auction in Exhibit Hall and Project Delay
901 Black Hawk Road
Waterloo, IA 50701
Ph : 319-236-2003
We are pleased to offer the following specifications and pricing to make the following changes:
Demobilization and remobilization, temporary lighting, temporary cooling and life safety for the duration of event in the exhibition hall
that is scheduled July 13-27th
Also a new substantial completion date of September 25th due to project delay from chiller project truss reinforcement and
shutdown for auction.
Pricing does not include moving materials off site. City has stated that they will get the AC unit operational for the event so that
pricing has been removed.
Description Labor Material Equipment Subcontract Other Price
Peters Project Management and General
Requirements, Demobilization and
Remobilization
Young Plumbing and Heating - Demobilization
and Remobilization
$3,978.00
$1,282.00
$3,978.00
$1,282.00
Young Plumbing and Healing - Man lift pickup $150.00 $150.00
and delivery
Continental - Demobilize and Remobilize $1,670.00 . $1,670.00
Black Hawk Electrical - Install temporary 52,270.00 $2,270.00
lighting for auction and remove after auction.
Demobilize, Remobilize, and extra lift rental.
Bond and insurance
Fee on Changes
If you have any questions, please contact me at 319-236-2003.
Subtotal: $9,350.00
$9,350.00 1.50% $140.25
$9,350.00 15.00% $1,402.50
$0.00
Total: $10,892.75
Submitted by: Tyler Kramer
Peters Construction Corp.
Approved by: OM& Hart
Date 7/13/2020
Page 1 of 1