HomeMy WebLinkAboutK. Cunningham - Final Qty Contract No. 942 7.27.2020CITY 01 WATERLOO, IOWA
FINAL QUANTIY SUMMARY
PROJECT: FY 2018 ANSBOROUGH AVENUE IMPROVEMENTS FROM U.S. 20 TO SAN MARNAN DRIVE,
CONTRACT NO, 942
Date Prepared: June 30, 2020
AMOUNT: $ 24,748.81 Increase
TO: K. CUNNINGHAM CONSTRUCTION CO., INC. , Contractor
You are hereby ordered to make the following changes from the plans and specifications or perform the
following extra work on your contract dated March 29, 2018.
A. Description of change to be made or extra work to be done:
Adjust original construction quantities to actual construction quantities.
B. Reason for ordering change or extra work:
As -built quantities varied for some bid items.
C. Settlement for cost of work to be made as follows:
Compensation already made to contractor through original bid items.
See attached summary.
Total Net Increase $24,748.81
CITY OF WATERLOO
BY: Quento. dart 7/27/2020 K. CUNNINGHAM CONSTRUCTION CO., INC.
Mayor
ATTEST:
Kelley 7/27/2020
Date CONTRACTOR
BY:
PRINTED NAME: 3 cWE.n/
City Clerk Date
TITLE: - res 1171
APPROVED:
7/i /.Zo
Date
7//4/A2
ity Engin-er Date