HomeMy WebLinkAboutPeters Construction Co CO #1 5_Bros Exhibit Hall Ceiling Reno - 6.22.2020June 5, 2020
DATE
Change Order
Document G701' - 2017
PROJECT: (Name and address)
5 Sullivan Brothers Convention Center
Exhibit Hall Ceiling Renovation,
Waterloo, IA.
OWNER: (Name and address)
City of Waterloo
715 Mulbeny Street
Waterloo, IA 50703
CONTRACT INFORMATION:
Contract For: General Construction
Project No: 19-23188
CHANGE ORDER INFORMATION:
Change Order Number: 001
Date: May 07, 2020 Date: June 5, 2020
ARCHITECT: (None and address)
& S Group, Inc. (1SG)
314 East 4th Street
Waterloo, IA 50703
CONTRACTOR: (Name and address)
Peters Construction Corporation
901 Black Hawk Road
PO Box 2940
Waterloo, IA 50704
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments
attributable to executed Construction Change Directives,)
A. To increase Substantial Completion Date from August 7, 2020 to August 28, 2020.
The original Contract Stun was
The net change by previously authorized Change Orders
The Contract Sum prior to this Change Order was
The Contract Sum will be unchanged by this Change Order in the amount of
The new Contract Sum including this Change Order will be
The Contract Time will be increased by Twenty- one (21) days.
The new date of Substantial Completion will be August 28, 2020.
S 939,810.00
$ 0.00
939,810.00
b 0.00
939,810.00
NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract
Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
I & S Group, Inc. (ISG)
Peters Construction Corporation City of Waterloo
ARCHITECT (Firm nmrne) CONTRACTOR (Firm name)
SIGNATURE
Nathan Compton, Architect/Project
Manager
OWNER (Finn name)
Quentin Hart
6
SIGNATURE SIGNATURE
Bradley Best, President Quentin Hart, Mayor
PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE
6/22/2020
DATE DATE
AIA Document G701" — 2017. Copyright 01979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. The "American
Institute of Architects. "AIA," the AIA Logo, and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document
was produced by AIA software al 11:21.59 ET on 06/05/2020 under Order No.2887812444 which expires an 07/12/2020, is not for resale, is licensed for one-time
use only, and may only be used in accordance with the AIA Contract Documents e Terms of Service. To report copyright violations, e-mail copyright@aie.org.
User Notes: (3B9ADA4E)