HomeMy WebLinkAboutPeters Construction Co CO #1 5_Bros Exhibit Hall Ceiling Reno - 6.22.2020June 5, 2020 DATE Change Order Document G701' - 2017 PROJECT: (Name and address) 5 Sullivan Brothers Convention Center Exhibit Hall Ceiling Renovation, Waterloo, IA. OWNER: (Name and address) City of Waterloo 715 Mulbeny Street Waterloo, IA 50703 CONTRACT INFORMATION: Contract For: General Construction Project No: 19-23188 CHANGE ORDER INFORMATION: Change Order Number: 001 Date: May 07, 2020 Date: June 5, 2020 ARCHITECT: (None and address) & S Group, Inc. (1SG) 314 East 4th Street Waterloo, IA 50703 CONTRACTOR: (Name and address) Peters Construction Corporation 901 Black Hawk Road PO Box 2940 Waterloo, IA 50704 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments attributable to executed Construction Change Directives,) A. To increase Substantial Completion Date from August 7, 2020 to August 28, 2020. The original Contract Stun was The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be unchanged by this Change Order in the amount of The new Contract Sum including this Change Order will be The Contract Time will be increased by Twenty- one (21) days. The new date of Substantial Completion will be August 28, 2020. S 939,810.00 $ 0.00 939,810.00 b 0.00 939,810.00 NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. I & S Group, Inc. (ISG) Peters Construction Corporation City of Waterloo ARCHITECT (Firm nmrne) CONTRACTOR (Firm name) SIGNATURE Nathan Compton, Architect/Project Manager OWNER (Finn name) Quentin Hart 6 SIGNATURE SIGNATURE Bradley Best, President Quentin Hart, Mayor PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE 6/22/2020 DATE DATE AIA Document G701" — 2017. Copyright 01979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects. "AIA," the AIA Logo, and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software al 11:21.59 ET on 06/05/2020 under Order No.2887812444 which expires an 07/12/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents e Terms of Service. To report copyright violations, e-mail copyright@aie.org. User Notes: (3B9ADA4E)