HomeMy WebLinkAboutCardinal Construction CO_#4_-_5_Sull_Bros_Penthouse_Chiller 9.8.2020 *AI-XDocument G701" — 2017
Change Order
PROJECT:(Nance and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION:
5 Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:004
Penthouse Chiller for the City of Project No. 19-23141
Waterloo,IA.
Date:March 27,2020 Date:August 31,2020
OWNER:(Nance and address) ARCHITECT:(Name and address) CONTRACTOR:(Name-and address)
City of Waterloo I&S Group,Inc.(ISG) Cardinal Construction,Inc.
715 Mulberry Street 314 East 4th Street 1246 Martin Road
Waterloo,IA 50703 Waterloo,1A 50703 Waterloo,IA 50701
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and,ttapplicable,attach or reference spect6c exhibits.Also include agreed upon adjustments
attributable to executed Construction Change Directives.)
A. CR 03: Cost to add additional bus duct and make modifications to the bits duct to add
a new 1600 amp panel board for the new&future chillers.................................................Add $51,468.49
REDUCE SPECIFIED ELECTRICAL PANEL ALLOWNACE FROM$15,000 TO ZERO.
REDUCE REMAINING BALANCE OF GENERAL ALLOWANCE FROM$18,734.44 TO ZERO.
TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$17,734.05.
The original Contract Sum was S 1,114,000.00
The net change by previously authorized Change Orders $ 4,665,94
The Contract Sum prior to this Change Order was $
The Contract Sum will be increased by this Change Order in the amount of $ 17 734,05
The new Contract Sum including this Change Order will be $ 1,136,399.99
The Contract Time will be unchanged by Zero(0)days.
The new date of Substantial Completion will be August 7.2020.
NOTE:This Change Order does not include adjustments to the Contrast Sum or Guaranteed Maximum Price,or the Contract
Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER.
I&S Grou2,Inc. ISG, l Construction,Inc. City of Waterloo
ARCHITECT(P. l narne) C CTOR(Firm name) OWNER(Firm name)
iGNATU E SI ATURE SIGNATURE
Daniel C.Charmer Senior Architect Katy Suson&President Quentin Han_Mayor
PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE
August 31,2020 _ 8/31/20 9/8/2020
DATE DATE DATE
AIA document 0701"-2017.Copyright 01979,1987,2000.2001 and 2017 by The American Institute of Architects.Ali rights reserved.The'American
institute of Air-hltects, 'Alfa,'the AIA Logo,and'AIA Contract Docurnents'are i'egisrered lyddemark,end may not be used without permission.This document 1
was produced by AIA software at 12:22:41 ST on 08131/2020 under Order No.8114132283 which expires on 0711212021,Is not for resale,is licensed for one-time
use only,and may only be used in accordance with the AiA Contract Documents®Terms of Service.To report copyright violations,e-mail copyright@oio.org.
User Notes: (3139ADA39)