Document G701 " . 2017
Chimgt-. Order
PROJECT:(Maine and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION:
5 Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:001
2020 Skywalk Improvements,Waterloo, Project No: 19-23770
IA.
Date:May 07,2020 Date:October 19,2020
OWNER:(Nrune and address) ARCHITECT:(Name and address) CONTRACTOR:(Nance and address)
City of Waterloo I&S Group,Inc.(ISG) Woodruff Construction,LLC
715 Mulberry Street 314 East 4th Street 1717 Falls Avenue
Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,IA 50701
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and,if applicable,attach or reference specific exhibits.Also include agreed ripon adjustments
atiributable to executed Comtruction Change Directives.)
A. PCZ 05: Cost for Water Infiltration Exploration........................................................ Add $8,849.00
REDUCE SPECIFIED GENERAL ALLOWANCE FRONT$10,000.00 TO$1,151.00.
CONTRACT SUM REMAINS UNCHANGED.
The original Contract Sum was $ 199,890.00
The net change by previously authorized Change Orders $ 0.00
The Contract Sum prior to this Change Order was $ 199,890.00
The Contract Sum will be unchanged by this Change Order in the amount of $ 0.00
The new Contract Sum including this Change Order will be $ 199,890.00
The Contract Time will be unchanged by Zero(0)days.
The new date of Substantial Completion will be August 21,2020.
NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract
Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL.SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER,
I&S Group,Inc.(ISG) Woodruff Construction,LLC City of Waterloo
ARCHITECT(Finn name) CONTRACTOR(Fir ante) OWNER(Ficin name)
D(MRtin Hart
SIGNATURE SIG URE SIGNATURE
Nathan Compton,Architect/Project ohn Mallen,Project Manager Quentin Hart,Mayor
Manager
PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE
October 19,2020 10-19-20 10/26/2020
DATE DATE DATE
AIA Document G701 —2017.Copyright(D 1979,1987,2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The"American
Instilute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are registered tradernarks and!nay riot be used without permission-This document
was produced by AIA software at 17:10:55 ET on 10!19!2020 under Order No.8114132283 which expires on 07112/2021,is not for resale,is licensed for one-time
use only,and may only be used in accordance with the RIA Contract DDcumentsO Terms of Service.To report copyright violations,e-mail oopyrighl@aia.org.
User Notes: (3B9ADA3F)