HomeMy WebLinkAboutBrock Even Construction, Cont. No. 1009 Final Qty Summary.11.9.2020 CITY OF WATERLOO, IOWA FINAL QUANTITY ADJUSTMENT PROJECT: F.Y. 2020 SIDEWALK & TRAIL REPAIR PROGRAM —ZONE 10 CONTRACT NO. 1009 Date Prepared: October 9, 2020 AMOUNT:_�3,198.15 INCREASE TO: BROCK EVEN CONSTRUCTION LLC , Contractor You are hereby ordered to perform the following extra work on your contract dated April 13, 2020. A. Description of extra work to be done: Adjust original construction quantities to actual construction quantities. B. Reason for ordering extra work: As-built quantities varied for some bid items. C. Settlement for cost of extra work to be made as follows: Compensation already made to contractor through bid items. See attached summary. TOTAL INCREASE $31198.15 BY: 11/9/2020 BROCK EVEN CONSTRUCTION, LLC Mayor Date CONTRACTOR BY: Date ATTEST: TITLE: ,�� Kelle4( �'elchle 11/9/2020 j City Clerk Date APPROVED: �o a3 ad ity Engineer Dat Final Qty. Adj. Cont # 1009 Sheet 1 of 2