Loading...
HomeMy WebLinkAboutAECOM Supplement Agmnt No. 1 - Levee Sanitary Gatewell Repair Project 11.23.2020AECOM AECOM 319-232-6531 tel 501 Sycamore Street 319-232-0271 fax Suite 222 Waterloo, Iowa 50703 www.aecom.com SANITARY SEWER GATEWELL REPAIR PROJECT CITY OF WATERLOO, IOWA SUPPLEMENTAL AGREEMENT NO. 1 WHEREAS, a Professional Services Agreement was entered into between the City of Waterloo, Iowa, (Client), and AECOM Technical Services, Inc. (ATS), of Waterloo, Iowa, dated June 26, 2017, for the repair of thirty-seven (37) sanitary gatewells along the Cedar River levee system in Waterloo; and WHEREAS, the Client and ATS now desire to enter into Supplemental Agreement No. 1 for additional design services to create contract documents for two separate gatewell projects. NOW THEREFORE, it is mutually agreed to amend the original Professional Service Agreement as follows: I. Project Description The project consists of repairing, replacing and investigating thirty-two sanitary gatewells along the Cedar River and Black Hawk Creek levee system in Waterloo. Pipe sizing through gatewells range in size from 6" to 60". The project also includes replacing existing valves with gates where the sanitary crosses through the levee. There is also approximately 1,400 feet of sanitary sewer installation. The project utilizes State Revolving Fund (SRF) funding and necessary Army Corps of Engineers and Iowa Department of Natural Resources permitting. This project was originally bid in April of 2020 as one project. To allow for the funding of the project to be spread over additional fiscal years, it was desired to separate the original project into two smaller projects to be bid at different times. The first of the two projects will address the gatewells where the replacement of the gate within the existing gatewell structure is required where excavation is not planned. The second project will address the gatewells that require full replacement of the structure and appurtenances where excavation is required. The second project will also include installation of the proposed sanitary sewer. II. Scope of Services The Scope of Services will encompass and include detailed work, services, materials, equipment, personnel and supplies necessary to create contract documents for the two projects discussed above. The projects will each be divided into two phases. The first phase will include design services, including the preparation of plans and specifications in a format suitable for City of Waterloo lettings. The second phase will include construction -related services, which will be determined at the time the services are needed. Design Services The Scope of Services for the Design Phase is further defined as follows: Task 1 - Kickoff Meeting. With the City of Waterloo and ATS staff, a kickoff meeting will be conducted to discuss scope of project, objectives and goals for the two projects. Task 2 - Plans and Specifications. Prepare plans and specifications for each project. Plans will include cover sheet, general notes, plan and profile sheets, site locations for work, gatewell details, reference information of existing gatewells, site restoration items and details as necessary. Specifications will include contract documents incorporating requirements from the City of Waterloo. SUDAS specifications will be referenced. Required SRF documents necessary for bidding the project will be included. AECOM Page 2 Task 3 - Permitting. ATS will provide information to the Army Corps of Engineers, if requested, regarding the two projects. ATS will update Iowa DNR with the project and prepare an additional construction permit application or provide requested information for the Iowa DNR wastewater section, if needed. ATS will prepare application for the Notice of Intent for NPDES coverage under the General Permit. Task 4 - Engineer's Opinion of Probable Costs. An Engineer's Opinion of Probable Costs will be developed for each project. Task 5 - Preparation and Distribution of Contract Documents. Prepare contract documents for distribution to plan rooms and potential bidders for each project. Task 6 - Respond to Bidders Questions. Respond to questions that bidders may have regarding the projects. Prepare addenda as needed for each project. Task 7 - Attend Bid Opening. Attend bid openings, secure contracts, bonds and certificates of insurance, review bids, prepare bid tabulation and make recommendation to the City of Waterloo for each project. Task 8 - Project Administration, Coordination and Meetings. This task includes project administration, coordination and meetings throughout the project development. Up to four meetings with the City are included. Phase II - Construction -Related Services The scope of construction -related services will be determined at the time the services are needed and defined under a future amendment to this agreement. Construction -related services include construction staking, on -site field review, materials testing, contract administration during construction and right-of-way staking. III. Compensation Compensation for the above services will be on an hourly basis in accordance with Part VI of the original agreement and shall be integrated with the fees in the original agreement. The estimated fee is Sixty -Nine Thousand Nine Hundred Dollars ($69,900.00). IV. In all other respects, the obligations of the Client and the Consultant shall remain as specified in the Professional Services Agreement dated June 26, 2017. IN WITNESS WHEREOF, the parties hereto have executed this Supplemental Agreement No. 1 as of the dates shown below: AECOM TECHNICAL SERVICES, INC. Douglas W. Sc indel, P.E. Associate Vice President APPROVED FOR CLIENT: By: GL„e-1-1- n H,r4 Date November 23, 2020 Date 11/23/2020 O:\AdministrationWGREE\SUPPLE\SA1 WAT San Sewer Gatewell Repair Project.docx