HomeMy WebLinkAboutWRH, Inc. Change Order No.2 Digester #3 12.7.2020STRAND
ASSOCIATES
Strand Associates, Inch
910 West Wingra Drive
Madison, WI 53715
(P) 608-251-4843
November 30, 2020
CHANGE ORDER NO. 2
PROJECT: FY 2020 Wastewater Treatment Plant Digester No. 3 Cover Modifications
OWNER: City of Waterloo, Iowa
CONTRACT: 1021
CONTRACTOR: WRH, Inc.
Description of Change
2a Change Contract completion dates as a result of cold ADD
weather.
TOTAL VALUE OF THIS CHANGE ORDER: ADD
Contract Price Adjustment
Original Contract Price
Previous Change Order Adjustments
Adjustment in Contract Price this Change Order
Current Contract Price including this Change Order
Contract Substantial Completion Date Adjustment
Original Contract Substantial Completion Date
Contract Substantial Completion Date Adjustments due to previous Change Orders
Contract Substantial Completion Date Adjustments due to this Change Order
Current Substantial Contract Completion Dates including all Change Orders
Contract Final Completion Date Adjustment
Original Contract Final Completion Date
Contract Final Completion Date Adjustments due to previous Change Orders
Contract Final Completion Date Adjustments due to this Change Order
Current Final Contract Completion Dates including all Change Orders
SKH:sjl51S:1MAD14400-44995446310081ConswcfioreChange Orders\CO 21CO 2.docx
$0.00
$0.00
$867,500.00
$0.00
$0.00
$867,500.00
October 14, 2020
21 Days
57 Days
December 31, 2020
November 13, 2020
21 Days
148 Days
May 1, 2021
Arizona I Illinois I Indiana I Kentucky I Ohio I Texas I Wisconsin www.strand.com
Strand Associates, Inc?
City of Waterloo, Iowa—WRH, Inc.
Contract 1021, Change Order No. 2
Page 2
November 30, 2020
This document shall become a supplement to the Contract and all provisions will apply hereto.
RECOMMENDED
ENG ER —Strand Associates, Inc.®
APPROVED
Date
12/1/2020
CONTRACTOR—WRH, Inc. Date
APPROVED
l
12/7/2020
OWNER —City of Waterloo, Iowa Date
SKH•sjR1S:4MAD14400--449914463\0081ConstructionlChangc Ordcrs\CO 21CO 2.docx
www.strand.com