RESOLUTION NO. 2020-903
RESOLUTION APPROVING COMPLETION OF PROJECT
AND RECOMMENDATION OF ACCEPTANCE OF WORK
FOR WORK PERFORMED BY ASPRO, INC., OF WATERLOO,
IOWA, IN THE AMOUNT OF $3,222,553.02, IN
CONJUNCTION WITH THE FY 2020 ASPHALT OVERLAY
PROGRAM, CONTRACT NO. 992, AND RECEIVE AND FILE
A TWO-YEAR MAINTENANCE BOND.
WHEREAS, Aspro, Inc., of Waterloo, Iowa, performed work in conjunction with the FY
2020 Asphalt Overlay Program, Contract No. 992, and
WHEREAS Aspro, Inc., has completed the aforementioned project, in accordance with
the project plans and specifications as approved by Council April 27, 2020, Resolution No. 2020-
282, at a total cost of $3,222,553.02.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WATERLOO, IOWA, that the Certificate of Completion and Recommendation of Acceptance of
Work, for work performed by Aspro, Inc., at a total cost of $3,222,553.02, in conjunction with
the FY 2020 Asphalt Overlay Program, Contract No. 992, are hereby approved.
PASSED AND ADOPTED this 21st day of December 2020.