Loading...
HomeMy WebLinkAbout2020-903-12.21.2020Prepared by LeAnn M. Even, Deputy City Clerk, City of Waterloo, 715 Mulberry Street, Waterloo, IA 50703, 319-291-4323. RESOLUTION NO. 2020-903 RESOLUTION APPROVING COMPLETION OF PROJECT AND RECOMMENDATION OF ACCEPTANCE OF WORK FOR WORK PERFORMED BY ASPRO, INC., OF WATERLOO, IOWA, IN THE AMOUNT OF $3,222,553.02, IN CONJUNCTION WITH THE FY 2020 ASPHALT OVERLAY PROGRAM, CONTRACT NO. 992, AND RECEIVE AND FILE A TWO-YEAR MAINTENANCE BOND. WHEREAS, Aspro, Inc., of Waterloo, Iowa, performed work in conjunction with the FY 2020 Asphalt Overlay Program, Contract No. 992, and WHEREAS Aspro, Inc., has completed the aforementioned project, in accordance with the project plans and specifications as approved by Council April 27, 2020, Resolution No. 2020- 282, at a total cost of $3,222,553.02. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WATERLOO, IOWA, that the Certificate of Completion and Recommendation of Acceptance of Work, for work performed by Aspro, Inc., at a total cost of $3,222,553.02, in conjunction with the FY 2020 Asphalt Overlay Program, Contract No. 992, are hereby approved. PASSED AND ADOPTED this 21st day of December 2020. Quentin Hart, Mayor ATTEST: LeAnn M. Even, CMC, IaCMC Deputy City Clerk