HomeMy WebLinkAboutCardinal Contruction CO#4 - 5 Sullivan Bros CC Addition and Renovation - 02.01.2021 -:.• � Document G701 - 2017
Change Order
PROJECT:(Nance and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION:
Five Sullivan Brothers Convention Center Contract For.General Construction Change Order Number:004
Addition and Renovation,Waterloo,IA. Project No:20-23943
Date:September 08,2020 date:January 29,2021
OWNER:(Name and address) ARCHITECT:(Name and address) CONTRACTOR:(Narne and address)
City of Waterloo I&S Group,Inc.(ISG) Cardinal Construction,Inc.
715 Mulberry Street 314 East 4th Street 1246 Martin Road
Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,1A 50701
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description oj'Ihe change and, ij'applicahle, attach or reference specific ezliihif.s-Also include agreed upon adjusnirents
attributable to executed Consiniclivn Change Directives.)
A. Cost for Firewall Revisions per PR-03R..........................................................................................Add $88,881.00
TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$88,881.00,
The original Contract Sum was $ 5,516,300.00
The net change by previously authorized Change Orders $ 21,307.00
The Contract Sum prior to this Change Order was $ 5,537,607.00
The Contract Sum will be increased by this Change Order in the amount of $ 88,881.00
The new Contract Sum including this Change Order will be $ 5,626,488.00
The Contract Time will be unchanged by Zero(0)days.
The new date of Substantial Completion will be August 13,2021. Please reference attached comments regarding completion date.
NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract
Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER.
I&S Group,Inc.(TSG) Cardinal Construction,Inc. City of Waterloo
ARCHITECT(Firm name) CO CTOR(Finn name) OWNER(Fit-in naive)
SIGNATURE SIGNATURE SIGNATURE
Nathan Compton,Architect Katy Susong,President Quentin Bart,Mayor
PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE
January 29,2021 January 29,2021 2/1/2021
DATE DATE DATE
AIA Document G701'"—2017.Copyright(0 1979,1987,2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The"Amercar
Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are registered trademarks and may not be used without permissions.This document
was produced by AIA software at 16:49:18 ET on 01/29/2021 under Order No.8114132283 which expires on 0711212021,is not for resale,is licensed for one-lime
use only,and may only be used in accordance with the AIA Contract Documentse Terms of Service.To report copyright violations,e-mail copyright@aia.org.
User Notes: (3139ADAQ)
CARDINAL
CONSTRUCTION
Five Sullivan Brothers Convention Center Addition & Remodel
Date: January 29, 2021
The overall substantial completion date of the project will not be impacted by this PR, however, the March 19'
substantial completion date of the remodel portion of the project will be impacted due to the lead times of
materials and the time required for installation once materials are delivered. For example, the fire dampers will
not be released until this PR is approved and they have a 4 to 6 week lead time, plus install time, and time to
finish installing ceilings afterwards. Also, there appears to be an issue with the transfer fans that were just
approved. Plumb Tech needs to figure out exactly what the issue is, but they may not be delivered prior to the
March 191h date. Doors and hardware have a 7 t 9 week lead time, plus install time, and time to paint
afterwards. The only doors/frames/hardware not impacted by PR-3 are openings 124A, S4, and S6. These are the
only openings that have been released at this point.
1246 Martin Road
Waterloo, Iowa 50701
(319) 232-5400 P
(319) 232-2262 F
www.cardinalconst.com