HomeMy WebLinkAboutMidwest Concrete Final Quantity Summary - FY21 Sidewalk Repair Assessment Program Cont. No. 1018 02.01.2021CITY OF WATERLOO, IOWA FINAL QUANTITY ADJUSTMENT PROJECT: F.Y. 2021 SIDEWALK REPAIR ASSESSMENT PROGRAM — ZONE 10 CONTRACT NO. 1018 Date Prepared: January15,2021 AMOUNT:186,355.05 DECREASE TO: MIDWEST CONCRETE, INC. . Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated October 5, 2020. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction quantities. B. Reason for ordering change or extra work: As -built quantities varied for some bid items. C. Settlement for cast of work to be made as follows: Compensation already made to contractor through bid items. See attached summary BY: VCVeiI"�i/� f-7c,r- 2/1 /2021 Mayor Date ATTEST: Kellei �elchle 2/1/2021 City Clerk Date TOTAL DECREASE ONCRETE. INC. TITLE: (/ j'6'' teAl Cid APPROVED: ity Engineer $86,355.05 Date Final Qty. Adj. Contract No. 1018 Sheet 1 of 2 F.Y. 2021 SIDEWALK REPAIR ASSESSMENT CONTRACT NO. 1018 PROGRAM - ZONE 10 FINAL PERIOD: BASE CONSTRUCTION ITEMS BID ITEM ITEM DESCRIPTION UNIT ORIGINAL BID QUANTITY FINAL QUANTITY QUANTITY DIFFERENCE CONTRACTOR UNIT PRICE CONTRACTOR UNIT PRICE EXTENDED INCREASE / DECREASE 1 REM/REP SIDEWALK 4", PCC SF 28,364.8 21,906.4 (6,458.4) $ 8.50 $ 186,204.40 $ (54,896.40) 2 REM/REP SIDEWALK 5", PCC SF 1,667.5 2,736.2 1,068.7 $ 9.00 $ 24,625.80 $ 9,618.30 3 REM/REP SIDEWALK 6", PCC SF 6,674.5 4,534.5 (2,140.0) $ 10.00 $ 45,345.00 $ (21,400.00) 4 REM/REP CLASS "A" SIDEWALK SF 7,256.9 5,426.8 (1,830.1) $ 8.50 $ 46,127.80 $ (15,555.85) 5 PATCH EA 6.0 9.0 3.0 $ 20.00 $ 180.00 $ 60.00 6 CLEAN SIDEWALK EA 91.0 71.0 (20.0) $ 50.00 $ 3,550.00 $ (1,000.00) 7 WATER VALVE ADJUSTMENT EA 8.0 8.0 - $ 100.00 $ 800.00 $ - 8 WATER VALVE CAP EA 4.0 3.0 (1,0) $ 50.00 $ 150.00 $ (50.00) 9 VAULT TOP REPAIR SF 284.2 3.5 (280.7) $ 10.00 $ 35.00 $ (2,807.00) 10 DETECTABLE WARNING SURFACE SF 22.0 24.0 2.0 $ 40.00 $ 960.00 $ 80.00 11 SAW CUT LF 38.6 14.4 (24.2) $ 1.00 $ 14.40 $ (24.20) 12 LF 37.0 37.1 0.1 $ 40.00 $ 1,484.00 $ 4.00 CURB & GUTTER REPAIR 13 REM/REP 6" PCC W/CURB SF 54.5 57.8 3.3 $ 20.00 $ 1,156.00 $ 66.00 14 JOINT SEAL LF 19.5 0.0 (19.5) $ 1.00 $ - $ (19.50) 15 TRIM TREE/SHRUBS EACH 44.0 12.0 (32.0) $ 50.00 $ 600.00 $ (1,600.00) BASE CONSTRUCTION TOTAL $ 311,232.40 $ (87,524.65) CHANGE ORDER ITEMS BID ITEM ITEM DESCRIPTION UNIT ORIGINAL BID QUANTITY FINAL QUANTITY QUANTITY DIFFERENCE CONTRACTOR UNIT PRICE CONTRACTOR UNIT PRICE EXTENDED INCREASE / DECREASE 1001 3/4" ROADSTONE TON 15.0 35.6 20.6 $ 30.00 $ 1,068.00 $ 618.00 1002 MANHOLE ADJUSTMENT, MINOR EA 1.0 2.0 1.0 $ 500.00 $ 1,000.00 $ 500.00 1003 REMOVE SIDEWALK, BACKFILL WITH TOPSOIL, GRADE, AND SEED SF 395.6 395.6 - $ 6.00 $ 2,373.60 $ - 2001 VAULT TOP REPAIR - TEMPORARY LS 1.0 1.0 - $ 1,000.00 $ 1,000.00 $ - 2002 TREE GRATE ADJUSTMENT LS 1.0 1.0 - $ 1,700.00 $ 1,700.00 $ - 3001 REMOVE PCC SIDEWALK SF 250.0 262.9 12.9 $ 4.00 $ 1,051.60 $ 51.60 CHANGE ORDER ITEMS TOTAL $ 8,193.20 $ 1,169.60 CONSTRUCTION ITEMS TOTAL $ 319,425.60 $ (86,355.05) PAYMENTS AMOUNT PAY ESTIMATE #1 $ 105,952.88 $ 83,804.87 PAY ESTIMATE #2 PAY ESTIMATE #3 $ 114,745.99 PAY ESTIMATE #4 $ 453.86 RETAINAGE $ 14,468.00 TOTAL PAYMENTS $ 319,425.60 CHANGE ORDERS AMOUNT CHANGE ORDER #1 $ 3,323.60 CHANGE ORDER #2 $ 2,700.00 CHANGE ORDER #3 $ 1,000.00 CHANGE ORDER TOTAL $ 7,023.60 ORIGINAL CONTRACT AMOUNT $ 398,757.05 CHANGE ORDER TOTAL $ 7,023.60 REVISED CONTRACT AMOUNT $ 405,780.65 FINAL QUANTITY SUMMARY $ (86,355.05) FINAL CONTRACT AMOUNT $ 319,425.60 FINAL QUANTITY ADJUSTMENT CONTRACT 41018 SHEET 2 OF 2