CITY OF WATERLOO,IOWA
CHANGE ORDER NO. 1
PROJECT: Airline Highway Sanitary Sewer Extension CONTRACT NO. 979
Date Prepared: 1/25/2020 AMOUNT: Increase $19,211.50
TO: PCI Contractor
You are hereby ordered to make the following changes from the plans and specifications or perform
the following extra work on your contract dated 1/1812020.
A. Description of change to be made or extra work to be done:
Add Item CO 1.1:8" Wattle Installation
Add Item CO 1.18" Wattle Maintenance
Add Item CO 1.3:8" Wattle Removal
Add Item CO 1.4:Recycled Special Backfill
Add Item CO 1.5:1.8" RCP
B. Reason for ordering change or extra work:
All items will be paid per unit cost as measured in the field.
Items 1-3 have been included to provide site erosion control devices.
Item 4 has been included in order to facilitate compaction under an existing driveway which
also includes multiple utility crossings,
Item 5 has been added for a field access culvert.
C. Settlement for cost of work to be made as follows:
Add Itern CD 1.1:8"Wattle Installation x 800 LF at$3.60/LF=+$2,880.00
Add Item CO 1.2:8" Wattle Maintenance x 800 LF at$4.15/LF= +$3,320.00
Add Item CO 1.3:8" Wattle Removal x 800 LF at$0.55/LF=+$440.00
Add Item CO 1.4; Recycled Special Backfill x 518 TN at$19.25/TN=+$9,971.50
Add Item CO 1.5:18" RCI'x 40 LF at$65.00/LF=+$2,600.00
Total Net Increase $19,211,50
CITY OF WATERLOO, IOWA
BY: 0,e, ;^ 2/15/2021 fir!e rso n Conira Ctu r s Inc
Mayor Date COJT�
BYc(,
Date
ATTEST:
Kelley �elchle 2/15/2021 PRINTED NAME: Cardel 4 Q P{fit Soh
City Cleric Date
TITLE: presiderit
APPROVED:
ity Engineer Vate