Cardinal Construction CO #7, 5 Sullivan Bros. Penthouse Chiller 3.1.2021
r_— o Document G701 2017 Change Order PROJECT: (Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: 5 Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:007 Penthouse Chiller for the City of Project No. 19-23141 Waterloo,IA. Date:March 27,2020 Date:February 10,2021 OWNER:(Name and address) ARCHITECT:(Name and address) CONTRACTOR:(Name and address) City of Waterloo I&S Group,Inc.(LSO) Cardinal Construction,Inc. 715 Mulberry Street 314.East 4th Street 1246 Martin Road Waterloo,IA 50703 Waterloo,LA 50703 Waterloo, LA 50701 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and,if'applicahle,attach or reference specific exhibits.Also include agreed upon adjustments attributabte to executed Construction Change Directives.) A. CR 06: Cost to remove the sound attenuator on the supply fan, Remove and install new 16 ga.galvanized welded metal complete with fire wrap on the additional ductwork..........Add $6,345.18 B. CR 08: To move the unit heater called out for in ASI 4 so that electrical bus duct canbe installed.......................................................................................................................Add $2,001.12 TOTAL ADD $8,346.30 REDUCE SPECIFIED ROOF ASBESTOS ABATEMENT ALLOWANCE FROM$15,000.00 TO$6,653.70. CONTRACT SUM REMAINS UNCHANGED, The original Contract Sum was $ 1,1 14,000.00 The net change by previously authorized Change Orders $ 26,865.08 The Contract Sum prior to this Change Order was $ 1,140,865.08 The Contract Sum will be unchanged by this Change Order in the amount of $ 0.00 The new Contract Sum including this Change Order will be $ 1,140,865.08 The Contract Time will be unchanged by Zero(0)days. The new date of Substantial Completion will be August 7,2020, NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive. NOTVALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. I&S Group,Inc.(ISG) Cardinal Construction,Inc. City of Waterloo ARCHITECT(Firer Mane) 707RACTOR(Finn name) OWNER(Firm name) SIGNATURE MATURE SIGNATURE Nathan Compton,Architect/Project Katy Susong,President Quentin hlart,Mayor Manager Quentin Hart PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE February 10,2021 2-10-2021 3/1/2021 DATE DATE DATE AIA Document G701'°—2017.Copyright©1979,1987,2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The"American Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are registered trademarks and may not be used without permission,This document was produced by AIA software at 16:54:21 ET on 02/10/2021 under Order No-8114132283 which expires on 07112/2021.is not for resale,is licensed for one-lime use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail oopyrighl@aia.org. User Notes: (21HADA38)