HomeMy WebLinkAboutCardinal Construction - Convention Ctr Addition and Lobby Change Orders #6 thru #9 - 3.22.2021 = = o 1 Change Order PROJECT:(Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: Five Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:006 Addition and Renovation,Waterloo,IA. Project No:20-23943 Date:September 08,2020 Date:March 5,2021 OWNER:(Name and address) ARCHITECT:(Name and address) CONTRACTOR:(Name and address) City of Waterloo I&S Group,Inc.(ISG) Cardinal Construction,Inc. 715 Mulbei7y Street 314 East 4th Street 1246 Martin Road Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,IA 50701 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and,if applicable,attach or referencespecific exhibits.Also include agreed upon adjustments attributable to executed Construction Change Directives.) A. COR 06: Demo of two drain lines and plumbing for second floor drinking fountain that were inside of masonry walls called for demo(per PR 09)................................................... Add $795.00 TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$795.00. The original Contract Sum was $ 5,516,300.00 The net change by previously authorized Change Orders $ 110,629.06 The Contract Sum prior to this Change Order was $ 5,626,929.06 The Contract Sum will be increased by this Change Order in the amount of $ 795.00 The new Contract Sum including this Change Order will be $ 5,627,724.06 The Contract Time will be unchanged by Zero(0)days. The new date of Substantial Completion will be August 13,2021, NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. I&S Group,Inc.(ISG) Cardinal Construction,Inc. City of Waterloo ARCHITECT(Firm name) ! ACTOR(Firm name) OWNER I(Fin/n�name) /V � Qv¢ii'riil rlc,r'r aEol. SIGNATURE S ATURE SIGNATURE Nathan Compton,Architect Katy Susong,President Quentin Hart,Mayor PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE March 5,2021 March 8,2021 3/22/2021 DATE DATE DATE AIA Document G701'—2017.Copyright©1979,1987,2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The"American Institute of Architects,""AIA,"the AIA Logo,and'AIA Contract Documents"are registered trademarks and may not be used without permission.This document was produced by AIA software at 15:05:41 ET on 03/05/2021 under Order No.8114132283 which expires on 07/12/2021,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail copyright@aia.org. User Notes: (3139ADMA) - On Dcurnen , 64701 r, 2,017 Change Order PROJECT:(Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: Five Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:007 Addition and Renovation,Waterloo,IA. Project No:20-23943 Date:September 08,2020 Date:March 8,2021 OWNER:(Name and address) ARCHITECT:(Name and address) CONTRACTOR:(Nate and address) City of Waterloo I&S Group,Inc.(ISG) Cardinal Construction,Inc. 715 Mulberry Street 314 East 4th Street 1246 Martin Road Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,1A 50701 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and,if applicable,attach or reference specific exhibits.Also include agreed upon adjustments attributable to executed Construction Change Directives.) A. COR 07: Cost for addition coiling fire doors for the project.................................................................... Add$12,546.00 Note: Part of this cost will be paid by ISG,amount yet to be determined TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$12,546.00. The original Contract Sum was $ 5,516,300.00 The net change by previously authorized Change Orders $ 111,424.06 The Contract Sum prior to this Change Order was $ 5,627,724.06 The Contract Sum will be increased by this Change Order in the amount of $ 12,546.00 The new Contract Sum including this Change Order will be $ 5,640,270.06 The Contract Time will be unchanged by Zero(0)days. The new date of Substantial Completion will be August 13,2021. NOTE;This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. I&S Group,Inc.(ISG) C dint Construction,Inc. City of Waterloo ARCHITECT(Finn name) C ACTOR(Firm name) OWNER(Firm name) G?1�14;1 H114 SIGNATURE SIG TURE SIGNATURE Nathan Compton,Architect Katy Susong,President Quentin Hart,Mayor PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE March 8,2021 March 8,2021 3/22/2021 DATE DATE DATE AIA Document G701"—2017.Copyright©1979,1987,2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The"American Institute of Architects,"AIA,"the AIA Logo,and"AIA Contract Documents"are registered trademarks and may not be used without permission.This document was produced by AIA software at 12:31:47 ET on 03/08/2021 under Order No.8114132283 which expires on 07/12/2021,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail copyright@aia.org. User Notes: (3B9ADA3F) At -AV document Gro ', ` — 17 Change Order PROJECT:(Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: Five Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:008 Addition and Renovation,Waterloo,[A. Project No:20-23943 Date:September 08,2020 Date:March 10,2021 OWNER:(Name and address) ARCHITECT.(Warne and address) CONTRACTOR:(Natne and address) City of Waterloo I&S Group,Inc.(ISG) Cardinal Construction,Inc. 715 Mulberry Street 314 East 4th Street 1246 Martin Road Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,IA 50701 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and,if applicahle,attach or reference speck exhibits.Also include agreed upon adjustments attributable to executed Construction Change Directives.) A. Per ASI 004: Costs associated with added ceiling trim for lowered ceiling heights......................... Add$3,313.00 TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$3,313.00. The original Contract Sum was $ 5,516,300.00 The net change by previously authorized Change Orders $ 123,970.06 The Contract Sum prior to this Change Order was $ 5,640,270.06 The Contract Sum will be increased by this Change Order in the amount of $ 3,313.00 The new Contract Sum including this Change Order will be $ 5,643,583.06 The Contract Time will be unchanged by Zero(0)days. The new date of Substantial Completion will be August 13,2021. NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. T&S Group,Inc.(ISG) trdinal Construction,Inc. City of Waterloo ARCHITECT(Firm nante) CTOR(Firm name) OWNER(Finn name) SIGNATURE RE SIGNATURE Nathan Compton,Architect Katy Susong,President Quentin Hart,Mayor PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE March 10,2021 March 11,2021 3/22/2021 DATE DATE DATE AIA Document G701-—2017.Copyright©1979,1987,2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The"American Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are registered trademarks and may not be used without permission.This document was produced by AIA software at 17:29:25 ET on 03/10/2021 under Order No.8114132283 which expires on 07/12/2021,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail copyright@aia.org. User Notes: (3B9ADA40) I AIA Document 701 r ® 2017 Change Order PROJECT:(Marne and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: Five Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:009 Addition and Renovation,Waterloo,IA, Project No:20-23943 Date:September 08,2020 Date:March 16,2021 OWNER:(Nacre and address) ARCHITECT:(None and address) CONTRACTOR:(Nacre and address) City of Waterloo I&S Group,Inc.(ISG) Cardinal Construction,Inc. 715 Mulberry Street 314 East 4th Street 1246 Martin Road Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,IA 50701 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description ofthe change and,Ifapplicable,attach or reference specie exhibits.Also inchide agreed upon adjustnrenis attributable to executer/Construction Change Directives.) A. Per ASI 005: Removal of existing high soffit lighting fixtures attached to beam on exterior of the building;demo back to closestjunction........................................................Add $4,101.00 TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$4,101.00. The original Contract Sum was $ 5,516,300.00 The net change by previously authorized Change Orders $ 127,283.06 The Contract Sum prior to this Change Order was $ 5,643,583.06 j The Contract Sum will be increased by this Change Order in the amount of $ _ 4,101.00 The new Contract Sum including this Change Order will be $ 5,647,684.06 The Contract Time will be unchanged by Zero(0)days. The new date of Substantial Completion will be August 13,2021. NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. i I&S Croup,Inc.(ISG) Cardinal Construction,Inc. _City of Waterloo ARCHITECT(Firm name) CONTR�b'inn name) OWNER(Finn name) SIGNATURE SIGNATURE — SIGNATURE s`� Nathan Compton,Architectf Ct C� IfetriSnaetll;-Ptesientdeut Quentin Hart,Mayor PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE I March 16,2021 DATE DATE DATE I I i I AIA Document G701"-2017.Copyright©1979,1907,2000,2001 end 2017 by The American Institute of Archltects.All rights reserved.The"American Inslilute,of Architects,"AIA;the AIA Logo,and'AIA Contract Documents'are registered trademarks and may not be used vdihout permission.This document .� eras produced by AlA software at 13:08:00 ET on 03116/2021 under Order No.8114132283 which expires on 07/12/2021,Is not for resale,Is licensed for ane-time use only,and may only bo used in accordance with the AIA Contract Documents°Terms of Service.To report copyright violations,e-mail copyright@ala.org. User Notes: (3B9ADA40)