HomeMy WebLinkAboutKidder Construction - CO #5 Truck Wash Project 4.5.2021 - . -AIA-0.,: Document G701 - . 2017 Change Order PROJECT:(Nance and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: Public Warks Truck Wash Area Contract For:General Construction Change Order Number:005 Improvements for the City of Waterloo, Project No. 19-23490 Iowa, Date:July 30,2020 Date:Marc h 23,2021 OWNER:(Name and address) ARCHITECT:(Name and address) CONTRACTOR:(Name and address) City of Waterloo I&S Group,Inc,(ISO) Kidder Construction,Inc. 715 Mulberry Street 314 East 4th Street 6036 Foulk Road Waterloo,IA 50703 Waterloo,IA 50703 PO Box 2242 Waterloo lA 50704 THE CONTRACT IS CHANGED AS FOLLOWS: (7nser[a detailed description of the change and,ifapplicable,attach or reference speck exhibits.Also inchrde agreed apon adjustments attributable to execuled Construction Change Directives.) A. PR 04: Rerouting of the drain and rework of the high pressure wash equipment: Cost to provide work to(2) Cored(toles thru wall for lark drain, backflow preventer and water softener. Relocating 925 gallon talk back tolvard wall for better access to floor drain.......................................................................................Add $7,788.61 TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$7,788.61. The original Contract Sum was $ __ 302,574.00 The net change by previously authorized Change Orders $ -2,634,67 The Contract Sum prior to this Change Order was $ 299,939.33 The Contract Sum will be increased by this Change Order in the amount of $ 7,788.61 The new Contract Sum including this Change Order will be $ 307,727.94 The Contract Timo will be unchanged by Zero(0)days. The new date of Substantial Completion will be November 30,2020, NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. I&S Croup.Inc.(TSG) Kidder Construction,Inc. City of Waterloo ARCHITECT if'irnr name) CONT TOR(Firm name) OWNER(Firm name) SIGNATURE SIGNATURE SIGNATURE Nathan Compton,Architect(Project Lonnie Kidder Quentin Hart,Mayor Manager PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE March 23,2021 i1�r�7;'crj�. J f 4/5/2021 DATE DATE ~ DATE AIA Document G701 —2017.Copyright 01979,1987,2000,21101 and 2017 by The American Institute of Architects.All rights reserved.The-American tnslilr.te of Architects,""AIA,"the AIA Loge,and'AIA Contract Documents"are registered trademarks and may not be used without permission.This document was produced by A1A software at 12:09:44 ET on 0312312021 under Order No.0114132283 which expires on 07/1212021,Is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documentse Terms of Service.To report copyright violations,e-mail copydghtQais.org. User Notes: (3B9ADA3E) March 22, 2021 CONSTRUCT/ON Inc. ISG Nathan Compton nathan .comr)ton@isa .com RE: PR #04 Waterloo Public Works Truck Wash Improvements We propose to furnish material, labor, equipment, and insurance to complete the following for the sum of: $ 7,788.61 . We have included all items listed from John Trickles email sent on March 15, 2021 . Including: • (2) Cored holes thru wall for tank drain, backflow preventer, and water softener. • Relocating 925 gallon tank back toward wall for better access to floor drain . Costs : Stein Heating and Cooling per quote dated March 18, 2021 .. $ 6,975 .55 Bonding. 1 9 P a a 6 & a a a 0 0 a 9 6 9 a V 6 . a 6 0 0 0 a 0 0 $ 105.00 Kidder Construction Inc. - 10% O &P . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 708.06 Total amount of quote for PR #41 1 1 a a a 0 6 6 a 4 0 a 0 0 0 0 9 0 0 0 a a a a P 1 4 0 6 $ 7,788.61 Please let us know how to proceed . Thank you Kidder Construction Inc. Loww%e ICtdder 6036 Foulk Road Shop / Warehouse P. O . Box 2242 Waterloo , Iowa 50704 ( 319 ) 234 - 2259 FAX ( 319 ) 233 - 5690 . STEIN HEATING & COOLING INC. Estimate 1120 E. 2nd St. Webster City, IA.50595 Date estimate # 3/18/2021 2010-230 Name / Address Kidder Construction Inc. 6036 Foulk Road P.O. Box 2242 Waterloo, IA 50704 Project CR #3 high pressure ... Description Qty Rate Amount Markup Total CR # 3 Rerouting of the drain and rework of the redesign of the high pressure wash equipment piping labor to install 40 75.00 31000.00 3,000.00 office labor 1 75.00 75.00 75.00 materials 32900.55 32900.55 31900.55 Total $6,975.55