HomeMy WebLinkAboutCardinal Constlruction CO#10 5 Sullivan Bros. CC Addition and Lobby Reno - 4.19.2021 AIA
Document G701 - 2017
Change Order
PROJECT:(Nmne and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION:
Five Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:010
Addition and Renovation,Waterloo,[A. Project No:20-23943
Date:September 08,2020 Date:March 30,2021
OWNER:(Naive and address) ARCHITECT:(Name and address) CONTRACTOR:(Nance and address)
City of Waterloo I&S Group,Inc.(ISG) Cardinal Construction,Inc.
7 1.5 Mulberry Street 314 East 4th Street 1246 Martin Road
Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,IA 50701
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and,ij'applicable,attach or reference specific exlrihits.Also include agreed upon adjustments
attributable to executed Construction Change Directives.)
A. PR 09: Credit to Owner for Window changes..............................................................................Deduct ($ 947.90)
B. PR 11: Credit to Owner for Roller Shade(s)changes...................................................................Deduct ($1,0$5.00)
TOTAL DEDUCT ($2,032.90)
TOTAL AMOUNT OF THIS CHANGE ORDER,DEDUCT FROM CONTRACT SUM($2,032.90).
I
The original Contract Sum.was $ 5,516,300.00
The net change by previously authorized Change Orders $ 131,384.06
The Contract Sum prior to this.Change Order was $ 5,647,684.06
The Contract Sum will be decreased by this Change Order in the amount of $ 2,032.90
The new Contract Sum including this Change Order will he $ 5,645,651.16
The Contract Time will be unchanged by Zero(0)days.
The new date of Substantial Completion will be August 13,2021,
NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract
Time,that have been authorized by Construction Change Directive until the cost and tone have been agreed upon by both the
Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNER BY THE ARCHITECT,CONTRACTOR AND OWNER.
I&S Group,Inc.(ISG) Cardina Construction,Inc. City of Waterloo
ARCHITECT(Finn name) CONTR (Firm name) OWNER(Finn naine)
SIGNATURE SIGNAT R SIGNATURE
_Nathan Compton,Architect Katy Susong,President Quentin Hart,Mayor
PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE
March 30,2021 March 30,2021 4/19/2021
DATE DATE DATE
AIA Document G701"—2017.Copyright®1979,1967,2000,2001 and 2017 by The American Institute of Architects.All rights reserved,The"American
Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are registered trademarks and may not be used without permission.This document
was produced by AIA software at 15:47:34 ET on 03/30/2021 under Order No.8114132283 which expires on Wit 212021,is not for resale,is licensed for one-time
use only,and may only be used in accordance with the AIA Contract Documents°Terms of Service.To report copyright violations,a-mail copyright@aia.org.
User Notes: (3139ADA40)