HomeMy WebLinkAboutAECOM - Supplemental Agreement No. 2, FY21 Sanitary Sewer Gatewell Repair - 4.19.2021 �0� AECOM 319-232- 1 tel
� 501 Sycamore Street 319-232-027027 1 fax
Suite 222
Waterloo,Iowa 50703
www.aecom.com
SANITARY SEWER GATEWELL REPAIR PROJECT
CITY OF WATERLOO, IOWA
SUPPLEMENTAL AGREEMENT NO. 2
WHEREAS, a Professional Services Agreement was entered into between the City of Waterloo, Iowa,
(Client), and AECOM Technical Services, Inc. (ATS), of Waterloo, Iowa, dated June 26, 2017,for the repair
of thirty-seven (37) sanitary gatewells along the Cedar River levee system in Waterloo; and
WHEREAS, the Client and ATS entered into Supplemental Agreement No. 1 on November 23, 2020, for
additional design services to create contract documents for two separate gatewell projects; and
WHEREAS, the Client and ATS now desire to enter into Supplemental Agreement No. 2 for construction-
related services for the Phase I project.
NOW THEREFORE, it is mutually agreed to amend the original Professional Service Agreement as follows:
I. Project Description
The project consists of repairing, replacing and investigating thirty-two sanitary gatewells along the
Cedar River and Black Hawk Creek levee system in Waterloo. Pipe sizing through gatewells range
in size from 6" to 60". The project also includes replacing existing valves with gates where the
sanitary crosses through the levee. There is also approximately 1,400 feet of sanitary sewer
installation. The project utilizes State Revolving Fund (SRF) funding and necessary Army Corps
of Engineers and Iowa Department of Natural Resources permitting.
This project was originally bid in April of 2020 as one project. To allow for the funding of the project
to be spread over additional fiscal years, it was desired to separate the original project into two
smaller projects to be bid at different times. The first project (Phase 1) will address the gatewells
where the replacement of the gate within the existing gatewell structure is required where
excavation is not planned. The second project (Phase 11) will address the gatewells that require
full replacement of the structure and appurtenances where excavation is required. Phase 11 will
also include installation of the proposed sanitary sewer.
This supplemental agreement provides construction-related services for the Phase I project.
II. Scope of Services
The Scope of Services will encompass and include detailed work, services, materials, equipment,
personnel and supplies necessary to provide construction-related services for the Phase I project
and associated engineering assistance to the City for the SRF process required for the project.
The Scope of Services is further defined as follows:
Task 1. Conduct a preconstruction conference attended by representatives of the Contractor,
Client, Consultant and affected utilities.
Task 2. Provide construction staking for horizontal and vertical controls for the project.
Task 3. Review shop drawings and other submittals as required of the Contractor by the contract
documents for conformance with the design concept of the project and compliance with the
information given in the contract documents.
AECOM Page 2
Task 4. Answer design interpretation questions from the Client, Contractor, review staff and
appropriate agencies.
Task 5. Prepare monthly applications for payment based on information provided by field review
staff and Contractor and forward to the Client for execution with recommendation for approval and
payment.
Task 6. Perform construction site visits by design personnel at appropriate stages of construction
to review the quality of the work and to determine whether the work conforms to the contract
documents.
Task 7. Prepare and assist the Client and Contractor in processing contract change orders.
Task 8. Provide periodic field observation during construction to review the work of the Contractor
to determine if the work is proceeding in general accordance with the contract documents and that
completed work appears to conform to the contract documents. Staffing requirements may be
adjusted during the project in relation to the level of construction activity.
Task 9. Report to the Client any work believed to be unsatisfactory, faulty or defective or does not
conform to the contract documents and advise the Client of any work that should be corrected or
rejected.
Task 10. Consider and evaluate Contractor's suggestions for modifications and report them with
recommendations to the Client.
Task 11. Facilitate construction progress meetings of project as needed and complete minutes for
each meeting. It is anticipated that when construction activities begin, meetings will be bi-weekly.
Task 12. Participate in a review of the project with the Client and review staff near project
completion and prepare a list of items to be completed or corrected.
Task 13. Participate in a field observation of the completed project with the Client and review staff
before a final application for payment is processed for the Contractor.
Task 14. Maintain files for correspondence, reports of the job conferences, shop drawings and
sample submissions, reproductions of original contract documents including addenda, change
orders, field modifications, additional drawings issued subsequent to the execution of the contract,
Engineer clarifications and interpretations of the contract documents, progress reports and other
project-related documents.
Task 15. Compile Equipment Manufacturer's and Vendors Operation & Maintenance (O&M)
material from Contractor and distribute one electronic and two hard copies of O&M manuals to the
Client at the completion of the project.
Task 16. Provide the Client with a copy of revised drawings of the construction plans (record
drawings)for the project based on the construction observation records of the field review staff and
the Contractor showing those changes made during construction considered significant.
Task 17. Prepare and assist the Client with the final close-out documentation received from the
Contractor.
�Com Page 3
III. Compensation
Compensation for the above services will be on an hourly basis in accordance with Part VI of the
original agreement and shall be segregated from the fees in the original agreement and
Supplemental Agreement No. 1. The estimated fee is Three Hundred Twenty Thousand Dollars
($320,000.00).
IV. In all other respects, the obligations of the Client and the Consultant shall remain as specified in
the Professional Services Agreement dated June 26, 2017.
IN WITNESS WHEREOF, the parties hereto have executed this Supplemental Agreement No. 2 as of the
dates shown below:
AECOM TECHNICAL SERVICES, INC.
By , Date April 19, 2021
Douglas W" P.E.
Associate Vice President
APPROVED FOR CLIENT:
VC✓2/I4irl
/1 c4
By: Date 4/5/2021
0:\Administration\AGREE\SUPPLE\SA2 WAT San Sewer Gatewell Repair CRS.docx