HomeMy WebLinkAboutWoodruff Construction - CO#3 Cont. No. 994 - 5.17.2021 $�, ST RANDASSOCIATES®
Strand Associates, Inc.°
910 West Wingra Drive
°rgo Madison,WI 53715
EXCELLENCE IN ENGINEERING (P)608.251.4843
April 26, 2021
Mr. Brian Bowman
City of Waterloo
3505 Easton Avenue
Waterloo, IA 50702
Re: F.Y. 2020 Wastewater Treatment Plant Biosolids Modifications Project
Contract No. 994
City of Waterloo, Iowa(City)
Dear Brian,
Change Order No. 3 for the Contract with Woodruff Construction related to the above-reference project
is enclosed. This change order captures several modifications to the original Contract resulting in an
addition of$36,738.00 to the Contract price.
As of April 1,2021,this project is 53 percent complete with 54 percent of the Contract time elapsed.The
total value of changes to the original Contract price are summarized in the table below.
Change Order Amount
Nos. 1 and 2 ADD $17,980.10
No. 3 ADD $36,738.00
Total ADD $54,718.10
The current change in the Contract price is 0.3 percent of the original Contract value.
Please call 608-251-4843 if you have any questions.
Sincerely,
STRAND ASSOCIATES, INC.°
Samuel K. Hocevar
Enclosure
SK}LIII\S:\MAD\4400-4499\4463\009\Construction\Change Orders\003\CO 3 Cover Letter docx
Arizona I Illinois I Indiana I Kentucky I Ohio I Texas I Wisconsin www.strand.com
$MSTRAND
1 ASSOCIATES'
Strand Associates, Inc
910 West Wingra Drive
oC Madison, WI 53715
EXCELLENCE IN ENGINEERING (P)608.251.4843
April 23, 2021
CHANGE ORDER NO. 3
PROJECT: F.Y. 2020 Wastewater Treatment Plant Biosolids Modifications Project
OWNER: City of Waterloo, Iowa
CONTRACT: City Contract No. 994
CONTRACTOR: Woodruff Construction
Description of Change
3a Amend Contract Substantial Completion date as a result ADD $0.00
of COVID-19 delay claim of 14 days for time lost
between October 30 and November 12, 2020.
Final Completion Date was amended as part of
Change Order No. 2.
3b Removal of existing concrete tank walls and debris ADD $3,634.00
encountered during excavation in accordance with cost
proposal dated April 19, 2021.
3c Demolish existing plumbing piping and appurtenances ADD $1,740.00
in Structure 330 identified in RFI 32 in accordance with
the enclosed cost proposal dated February 4, 2021.
3d Provide pipe insulation on 4-inch and larger ductile iron ADD $23,935.00
nonpotable water(W2) pipe in accordance with the
enclosed cost proposal dated March 12, 2021.
3e Provide aluminum roof curb in accordance with RFI 43 ADD $2,576.00
and subsequent correspondence included with the
enclosed cost proposal dated March 9,2021.
3f Provide a new acoustical ceiling in Room 33003 (Office ADD $2,128.00
and Laboratory) in Structure 330 in accordance with the
enclosed cost proposal dated February 9, 2021.
3g Add additional I/O to 180-PLC-2 in accordance with the ADD $2,725.00
enclosed cost proposal dated March 24, 2021.
TOTAL VALUE OF THIS CHANGE ORDER: ADD $36,738.00
Contract Price Adjustment
Original Contract Price $16,587,300.00
Previous Change Order Adjustments $17,980.10
Adjustment in Contract Price this Change Order $36,738.00
Current Contract Price including this Change Order $16,642,018.10
SKH:[II\S:\MAD\4400--4499\4463\009\Construction\Change Orders\003\CO 3.docx
Arizona I Illinois I Indiana I Kentucky 1 Ohio I Texas I Wisconsin www.strand.com
Strand Associates, Inc.
City of Waterloo, Iowa—Woodruff Construction
City Contract No. 994, Change Order No. 3
Page 2
April 23, 2021
Contract Substantial Completion Date Adjustment
Original Contract Substantial Completion Date January 2, 2022
Contract Substantial Completion Date Adjustments due to previous Change 0 Days
Orders
Contract Substantial Completion Date Adjustments due to this Change Order 14 Days
Current Substantial Contract Completion Dates including all Change Orders January 16, 2022
Contract Final Completion Date Adjustment
Original Contract Final Completion Date March 3, 2022
Contract Final Completion Date Adjustments due to previous Change Orders 14 Days
Contract Final Completion Date Adjustments due to this Change Order 0 Days
Current Final Contract Completion Dates including all Change Orders March 17, 2022
This document shall become a supplement to the Contract and all provisions will apply hereto.
,`��4►O� 5 S►p��i�fri
"S.5 -��c► ECOMMEN ED
=�=RANDALL
LU
16137 �BNSUI_TANT—Strand Associ t s, Inc.° Date
�'��� ., .• 'APPROVED
'��'���►/OiWP��,•�`` 4/30/21
CONT RrED
—Woodruff Construction Date
APPR
5/17/2021
OWNER—City of Waterloo, Iowa Date
SKH:III\S:\MAD\4400--A499\4463\009\Construction\Change Orders\003\CO 3.docx
www.strand.com