Loading...
HomeMy WebLinkAboutWRH, Inc. - CO #3 Cont. No. 1021 - 5.17.2021 ,e`, STRAND Strand Associates, Inc.' 910 West Wingra Drive 7-ro Madison,WI 53715 EXCELLENCE IN ENGINEERING (P)608.251.4843 April 30,2021 CHANGE ORDER NO. 3 PROJECT: FY 2020 Wastewater Treatment Plant Digester No. 3 Cover Modifications OWNER: City of Waterloo, Iowa CONTRACT: 1021 CONTRACTOR: WRH, Inc. Description of Change 3a Reuse existing wiring in accordance with Request for (DEDUCT) ($854.00) Information(RFI)No. 6 and the enclosed Change Authorization Request(CAR)No. 7 dated November 18,2020. 3b Adjust Allowance for Concrete Surface Repair from (DEDUCT) ($14,877.50) $16,500 to $1,622.50. 3c Adjust Allowance for Anaerobic Digester Cover ADD $13,620.00 Repair—Unidentified Repairs from$40,000 to $53,620 in accordance with CAR No. 3 dated January 12, 2021. 3d Adjust Allowance for Draft Tube Mixer Rehabilitation— (DEDUCT) ($16,042.00) Bearing Replacement from$95,000 to$78,598 in accordance with CAR No. 6 dated November 18,2020. 3e Adjust Allowance for Draft Tube Mixer Rehabilitation— ADD $8,684.00 Unidentified Mixer Repairs from$25,000 to $33,684 in accordance with CAR No. 6 dated November 18,2020. 3f Provide additional lid repairs to address leaks in ADD $46,336.00 existing welds identified during bubble testing in accordance with CAR No. 8 dated January 29, 2021. TOTAL VALUE OF THIS CHANGE ORDER: ADD $36,866.50 Contract Price Adjustment Original Contract Price $867,500.00 Previous Change Order Adjustments $8,510.00 Adjustment in Contract Price this Change Order $36,866.50 Current Contract Price including this Change Order $912,876.50 SKH:IIn\\\\strand.com\projects\MAD\4400--4499\4463\008\Construction\Change Orders\CO 3\CO 3.docx Arizona I Illinois I Indiana I Kentucky I Ohio I Texas I Wisconsin www.strand.com Strand Associates, Inc° City of Waterloo, Iowa—WRH, Inc. Contract 1021, Change Order No. 3 Page 2 April 30, 2021 Contract Substantial Completion Date Adjustment Original Contract Substantial Completion Date October 14, 2020 Contract Substantial Completion Date Adjustments due to previous Change Orders 78 Days Contract Substantial Completion Date Adjustments due to this Change Order 0 Days Current Substantial Contract Completion Dates including all Change Orders December 31, 2020 Contract Final Completion Date Adjustment Original Contract Final Completion Date November 13,2020 Contract Final Completion Date Adjustments due to previous Change Orders 169 Days Contract Final Completion Date Adjustments due to this Change Order 30 Days Current Final Contract Completion Dates including all Change Orders May 31,2021 This document shall become a supplement to the Contract and all provisions will apply hereto. RECO�IMENDE o.:L I E ER—Strand Associates,Inc.® Date APPROVED CONTRACTOR—WRH,Inc. Date APPROVED 5/17/2021 OWNER—City of Waterloo, Iowa Date SKH:IIn\\\\strand.com\projects\MAD\4400-1499\4463\008\Construction\Change Orders\CO MCO 3.docx www.strand.com