HomeMy WebLinkAboutBoomerang Corporation of Anamosa - CO #2 - Dry Run Creek, Cont. No. 877- 6.7.2021 CHANGE ORDER NO. 2 Owner City of Waterloo, Iowa Date May 19, 2021 Project Dry Run Creek Interceptor _ Owner's Contract No. City Contract No. 877 Contractor Boomerang Corporation Date of Contract Start December 23,2020 $4,267 662.00 You are directed to make the following changes in the Contract Documents. Description: Additions: • Hammond Avenue Boring -- Directtonal drill casing and gravity main across Hammond Avenue due to large boulders obstructing the boring process, for a lump sum of$110,000.00. • Alexandria Drive—External drop pipe increase from 8"to 12"and 36"storm sewer crossing for a lump sum of$13,314.86. • Texas Street Lift Station Generator Pad—Size increase of generator pad for a lump sum of$2,598.19. • Texas Street Lift Station Transformer Upgrade — Upgrades to the electric transformer was found to be required by MidAmerican Energy to be within current specifications for a lump sum of$60,318.72. For this change, Total ADDITIONS...................................................................... $186,231.77 Reason for Change Order: • During construction and boring under Hammond Avenue,multiple large boulders prevented the work to continue. Means and methods were changed by the Contractor to complete the task. • During Construction at Alexandria Drive, it was found that an external drop pipe increase from 8"to 12"and 36"storm sewer(previously unknown)crossing was necessary. • To accommodate the provided acoustical enclosure for the Texas Street generator,the pad size needed to be increased. • During installation of the service connection to the existing electrical system at Texas Street,MidAmerican stopped work so that the existing transformer could be evaluated. It was determined that MidAmerican needed to upgrade the transformer at the site to meet current system specifications. This required a new transformer pad and new electrical wiring and conduits. CONTRACT PRICE CONTRACT TIMES (Calendar Days) To substantial To final completion completion Original: $4,267,662.00 Original Completion Date: November 30,2020 Previous C.O.'s(ADDIDEDUCT): $(263,111.68) This C.O.(ADDIDED1 IQT): $ 186,231.77 Contract Price with all REVISED Completion Date: TBD approved Change Orders: $4,190,782.09 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s)ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. APPFeVrED, . By: 6/7/2021 OWNER(Authorized Signature) Date ACCEPT D: BY: ;: ` k(1C ittl I C -77-tv,,.,1 /a l� f a u a CONTRACTOR(Authorized Signature) Date P:1605070761600 Construction Support1670 Change-Orders\00.0212021-05 CO 42-Boomerang.docx