HomeMy WebLinkAboutTricon Construction Group - CO #5 - FY20 Virden Creek Levee Improvements, Cont. No. 947 - 6.7.2021 CHANGE ORDER NO. 5 Owner City of Waterloo Date: 5/25/2021 Project F.Y.2020 Virden Creek Levee Improvements Owner's Contract No. 947 Contractor: Tricon Construction Group Date of Contact Start 3/6/2020 Contract Amount: $ 3,808,500.00 You are directed to make the following changes in the Contract Documents, Description: 4-9 Pavement,PCC,6-inch $ 62.10 /SY X 50 EA $ 3,105.00 4-10 Intake,6010.512(5W-512)Intake,18-Inch $ 4,600.00 /EA X 1 EA $ 4,600.00 4-11 Storm Sewer,Trenched,RCP,12-Inch $ 48.30 /LF X 350 SY $ 16,905.00 4-12 Connection to Existing Intake $ 2,012.50 /EA X 1 CY $ 2,012.50 TOTAL ADDITIONS $ 26,622.50 Reason for Change Order 4-9 Replacement of Existing Gates Park Parking Lot Pavement 4-10 Intake to Drain Low Spot in Gates Park Parking Lot 4-11 Gates Park Parking Lot Outlet Pipe System 4-12 Connection to Existing Intake CONTRACT PRICE CONTRACT TIME To Substantial To Final Completion Completion Original: $ 3,808,500.00 Original Completion Date: 11/20/2020' 11/20/2020 Previous C.O.s(ADD/DEDUCT) $ 41,723.77 This C.O.(ADD/DEDUCT) $ 26,622,50 Revised Completion Date: 8/2/20211 8/2/2021 Contract Price with all approved Change Orders: $3,876,846.27 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s)ordered herein, including all impact,delays,and acceleration costs. Other than the dollar amount and time allowance listed above,there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALLAPPLY HERETO. APPROVED: BY: Hc,r4 °sl Eo 6/7/2021 Owner(Authorized Signature) Date ACCEPTED: r� -} BY: S- of ! •0 Contractor(Authorized Si a ure) Date ACCEPTED: BY: _ 5-28-21 AECOM Date AECOM 60626987 I 5 Project No. C.O.No. Change Order#5 Virden Creek-Quantities SUDAS Estimated Unit Item SPEC Description Unit Quantity Price Total 13 7030 Sidewalk,PCC,4-inch SY 10.50 $ 45.00 $ 472.50 14 7040 Removal of pavement SY 50.00 $ 11.00 $ 550.00 31 9010 Hydraulic Seeding,Type 1(Permanent Lawn Mixture) ACRE 0.165 $ 3,800.00 $ 627.00 Total Additional Plan Item Costs $ 1,022.50 Change Order Items 4-9 7010-A Pavement,PCC,6-inch SY 50.00 $ 62.10 $ 3,105.00 4-10 6010-A Intake,6010.512(SW-512)Intake,18-inch EA 1.00 $ 4,600.00 $ 4,600.00 4-11 4020-A Storm Sewer,Trenched,RCP,12-inch LF 350.00 $ 48.30 $16,905.00 4-12 6010-D Connection to Existing Intake EA 1.00 $ 2,012.50 $ 2,012.50 Total Change Order Cost $26,622.50 Notes* 1.)SUDAS Specifications to be used for all items. 2.)6"parking lot paving SY price shall include removal of any existing material to meet 6"depth requirements. TRIGON CONSr RUCTf.❑NI GROUP www.triconcq.com May 13, 2021 746 58th Ave Ct SW Cedar Rapids, IA 52404 Daniel Kimball P 866.588.9516 AECOM 501 Sycamore St, Suite 222 Corporate Office 2245 Kerper Blvd Waterloo, IA 50704 Suite 2 Dubuque, IA 52001 Project: F.Y. 2020 Virden Creek Levee Improvements P 563.588.9516 Re: COR# 9 F 563.588.9519 Additional cost for drain tile per attached. Dirt to Turf($0.25/SF) Unit Price Southside Concrete 2,700.00 Vieth Construction Corp $20, 450 fq'666.66 Subtotal $23, 150 -46-,-300.88 OHP $3, 472 . 50 - &,44§49- Total $26, 622 . 50 , Note: Revision will be sent to include seeding cost after acreage is known. Approved By: Ron Richard 5/13/2021 Ron Richard—Tricon Construction Date GXVe/4111 Ha.r4 S 6/7/2021 City of Waterloo Date VIETH CONSTRUCTION CORPORATION 6419 NORDIC DR. CEDAR FALLS,IA 50613 Contact: ALEX WEBER Phone: 319-277-1006 Cell-319-404-4506 Fax: 319-277-3383 EXCLUSIONS: 1.BOND JOB NAME: VIRDEN CREEK DRAINTILE EXTRA 2.EROSION&TRAFFIC CONTROL WATERLOO,IA 3.FINE GRADING+-0.2' 4.DEWATERING 5.COMPACTION TESTING 6.SAW CUTTING PAVEMENT 7.SURVEY LAYOUT ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT 1 INTAKE SW-512 INTAKE 18" 1.00 EA 4,000.00 4,000.00 12" RCP 350.00 LF $42-0 $14,7 0 0 6,650.00 4 CONNECTION TO EXISTING INTAKE 11.001 EA 1 1,750.00 1,750.00 GRAND TOTAL $2 0, 4 5 0 NOTES: -TO INCREASE PIPE SIZE TO 8"-$21.75 PER LF -TO INCREASE PIPE SIZE TO 12"-$23 PER LF Page 1 of 1 V Z r - 0 IS JO :CALEINFEET% ii EXIST. WALL 0 CLEANOUT 0a EXIST. INTAKE -.0 3 (SUDAS 4040.232 TYPE A-2) 4" SIDEWALK BETWEEN 30 RIM EL. 856.45 RIM ELEV. 859.55 EXIST. SIDEWALK & EXIST. s INV. EL. 853.35 (12" NW) INV. ELEV. 855.20 BASKETBALL COURTS !� o o s INV. EL. 853.45 (6" E) _ ___ — 859.75 859.75 350'-6" NON-PERFORAaTED'SUBD % ii 12" RCP @ 0 . 80 859.75 859.80 i SW512INTAKE SW-604 TYPE 4A GRATE O N: 3,654,221.98 U + E: 5,236,545.12 1 FORM GRADE 859.55' Inv. EL. 856 . 25 (12"W) ) BOTTOM WELL 855.55' 1 t z z N , 2 F! Lu 0 Q ~3. 20 S Lu wLuO J W Lu Q lMA 0 LL K Lu T" 0 04 -� �• 1 / LL ' f DATE •� - L� 'i` NOVEMBER 4,2019 ` h L PROJECT NO y'r�� � • 80221881 ^�•� + '} � � FILENAME 41 J DRAWING NO f+ •. r w1 •� H SHEET NO z 1 ' w a+tc � � •ti i, ' w a+«F