HomeMy WebLinkAboutMidwest Concrete, Inc. - Cont. No. 1033 - 6.21.21 FINAL.QUANTITY ADJUSTMENT
Owner City of Waterloo Date: 5/25/2021
Project Waterloo Airport Water Main-Phase
Owner's Contract No. 1033 Contractor: Midwest Concrete,Inc.
Date of Contact Start 10/6/2020 Contract Amount: $ 254,230.32
You are directed to make the following changes in the Contract Documents. Description:
2 Replacement of Unsultable Backfill
Materials $ 26.00 /CY x -273 LF $ (7,098.00)
20 121n Wattles $ 2.70 /LF x -1.410.6 LF $ (3,808.62)
22 Urban Seed Mix-Permanent $ 3,800.00 /AC x -0.33 AC $ (1,254.00)
23 Urban Seed Mix-Temporary $ 500.00 /AC x -0.34 AC $ (170.00)
24 Rural Seed Mix-Temporary $ 500.00 /AC x -0.9 AC $ (450,00)
TOTALADDITIONS $ (12,780.62)
Reason for Change Order
2 Reduction In completed quantity.
20 Reduction In completed quantity.
22 Reduction In completed quantity.
23 Reduction In completed quantity.
24 Reduction In completed quantity.
CONTRACT PRICE CONTRACT TIMC
To Substantial To Final
Completion Completion
Original: $ 254,230.32 Original Completion Date: 11/20/2020 12/18/2020
Previous C.O.s(ADD/DEDUCT) $ 357.56
This C.O.(ADD/DEDUCT) $ (12,780.62) Revised Completion Date: 12/23/2020 5/3/2021
Contract Price with all approved
.Change Orders: $ 241,807.26
It Is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s)ordered herein,
Including all Impact,delays,and acceleration costs. Other than the dollar amount and time allowance listed above,there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPROVED• —
B 1_ f
Vcaner(Authorized Signature) Date
CCEPTED:
Contractor(Authorized Signature) Date
ACCEPTED:
BY: 2LL 2' 5/25/2021
AECOM Date
CITY OF WATERLOO AECOM
60633175 _
BY: ¢^+^ H«4 6/21/2021 Project No. Fin@IQty Adj
Mayor Date
ATTEST:
Kelley �elchle 6/21/2021
City Clerk Date