HomeMy WebLinkAboutWRH, Inc. - CO#9 - Cont. No. 907 - 7.6.2021 CHANGE ORDER NO. 9
Owner: City of Waterloo Date: June 22,2021
Project: Satellite Wet Well Rehabilitation
Owner's Contract No.: 907 Contractor: WRH,Inc.
Date of Contract Start: $ Original Contract: $1,839,380.00
You are directed to make the following changes in the Contract Documents. Description:
Additions:
• A deteriorated pipe was found within the Satellite Wet Well Valve Vault on the back side after the wet well was cleaned. Discussions with the City and the
Engineer determined that replacing the existing pipe would be necessary.
Core Drill and Pipe Replacement=$15,355.00
• A deteriorated odor control pipe was found within the Satellite Wet Well during construction. The pipe will be cut,removed,and the remaining pipe capped.
Cut and Remove Odor Control Pipe=$2,974.00
TOTAL ADDITIONS: $18,329.00
TOTAL DEDUCTIONS: (0.00)
NET CHANGE ORDER AMOUNT: $18,329.00
Reason for Change Order:
This change order will remove the existing corroded and deteriorated pipes within the Satellite Wet Well improving the safety,effectiveness,and
reliability of the wet well. The pipe within the well will be replaced. The odor control pipe remaining will be capped. These areas were not accessible
for evaluation prior to the beginning of construction,but it was known these were potential and likely additions to the project.
CONTRACT PRICE CONTRACT TIMES(Calendar Days)
To Substantial To Final
Completion Completion
Original: $ 1,839,380.00 Original:
Previous C.O.s(ADD/DEDUCT): $ 389,545.00 Previous C.O.s(ADD/99-1r ): 4
This C.O.(ADD/9RDI{ST): $ 18,329.00 This C.O.(ADD/DEDUCT): 17
Contract Price With All Approved
Change Orders: $ 2,247,254.00 REVISED:
Original Completion Date: October 1,2019
Revised Completion Date: To be Determined
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s)ordered herein,including all impact,delays,
and acceleration costs. Other than the dollar amount and time allowance listed above,there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
APPROVED:
Qveil�in
By: H-,4 G"a, 6/7/2021
City of Waterloo(Authorized Signature) Date:
ACCEPTED:
By: 6-73 - 21
WRH,Inc.(Authorized Siqnature) Date:
AECOM
60488465 9
Project No. Change Order No.
Pagel oft
P:\60488465\600_Construction_Support\670_Change-Orders\2020-06-22-CO#9-Satellite Wetwell-WRH.doc