Loading...
HomeMy WebLinkAboutCardinal Construction - CO #4 -5 Bros 2nd Floor Reno - 10.4.2021 =. AIA Document 0101 2017 Change Order PROJECT:(Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: Five Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:004 2nd Floor Renovation,Waterloo,]A. Project leo:20-24695 Date:May 26,2021 Date:September t3,2021 OWNER:(Name and address) ARCHITECT:(Name and address) CONTRACTOR:(Name and address) City of Waterloo 1&S Group,Inc.(ISG) Cardinal Construction,Inc. 715 Mulberry Street 314 Fast 4th Street 1246 Martin Road Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,IA 50701 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and, ij'applicable,attach or reference specific adiihits.Also include agreed upon adjustments aitrihutable to executed Construction Change Directives) A. COR 03 (PR 01): Provide a nciv roof hatch to allow for greater access to the existing penthouse......Add$13,960.00 TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$13,960.00. The original Contract Sun was $ 1,810,800.00 The net change by previously authorized Change Orders $ 7,628.00 The Contract Sum prior to this Change Order was $ 1,818,428.00 The Contract Sum will be increased by this Change Order in the amount of $ 13,960.00 The new Contract Sum including this Change Order will be $ 1,832,388.00 The Contract Time will be unchanged by Zero(0)days. The new date of Substantial Completion will be December 23,2021;New Final Completion Date:January 7,2022. NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Tirne,that have been authorized by Construction Change Directive until the cost and tune have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. I&S Group,Inc.(ISG) Ca final Construction,Inc. City of Waterloo ARCHITECT(Firne nante) COTOR(Firm name) OWNER(Finn n/a fine) 1 SIG/NATURE SIG URE SIGNATURE Nathan Compton,Architect/Project Katy Susong,President Quentin Hart,Mayor Manager PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE September 13,2021 September 13 2021 10/4/2021 DATE DATE DATE AIA Document G701-—2017.Copyright p 1979,1987,2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The"American Institute of Architects,""AIA,"She AIA Logo,and"AIA Contract Documents"are registered lrademarks and may not be used wPoul permission.This document was produced by AIA software at 13:28:30 ET on 09/13/2021 under Order No.9281462824 which expires an 07/1212022,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents"Terms of Service.To report copyright violations,e-mail copyright@aia.org. User Notes: (389ADA40)