HomeMy WebLinkAboutPeterson Contractors, CO #5, Cont. No. 1020 - 10.18.2021 CITY OF WATERLOO,IOWA CHANGE or EXTRA WORK ORDER NO. _05 PROJECT: Shauhs Road Reconstruction Project , CONTRACT NO. RM-8155(772)—9D-07 Date Prepared: 9-28-2021 AMOUNT: $59,945.66 Participating TO: Peterson Contractors Inc Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated 04/29/2021, A. Description of change to be made or extra work to be done: (1)Doubled Reinforced PCC Paving 9-24-21-$59,945.66 B. Reason for ordering change or extra work: Doubled reinforced PCC paving roadway around station(152+65 to 152+90) C. Settlement for cost of work to be made as follows: Participating $59,945.66 Total Net Increase $59,945.66 CITY OF WATERLOO,IOWA Digitally signed by Chris D.Fleshner DN:C=US,E-ctleshner@pcius.00m, Chris {ris D. FJesll.,nerGN=GhrisD.Fleshner APPROVED: Date:2021.09.2813:19:33-65'00' CONTRACTOR 10/18/2021BY: Chris D. Fleshner 9-29-21 City Engineer Date Date Project Manager TITLE: By: GZv,4-" 10/18/2021 Mayor Date Attest: y'gw 10/18/2021 City Clerk Date DEZERS�H PETERSON CONTRACTORS, INC . MAWACl"RS %011q� EXTRA WORK AUTHORIZATIO NEINNFCR � � IaWa PO Box Phone: 319-345-2713 Rembeck, Iowa 50669 Fax: 319345-2991 yV etersoncontractors.com Project Name: Shaulis Road Reconstruction PCI Job J9215 Dae: 09/24/21 Extra Work Autorizalion # Remarks or Description of Extra Work: Below is pricing for double reinforced paving from Sta. 152+4076 - 153+0077. Item # Description quantity Units BaseUnit % Mark Up % Discount AdjustedUnit Rae Total Amount 1 Double Reinforced PCC Paving 362. 10 SY $150.50 10.00% 0,00% $165.55 $59,945.66 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 Total Amount: $59,945.66 The work covered by this authorization shall be performed in accordance with the same terms and conditions to; included in the original contract. Work Authorized and Changes Approved by: Prime Contractor or Owner: Peterson Contractors., Inc. By: By: Chris D . Fleshner Title: Date: Date: 9/24/2021 1325 Rail 319,277,30 Cedar FallsalA 50613 i OWEN www.owenc corn CONTRACTING September 23, 2021 RE: Shaulis Road Reconstruction - Hess Road to US 218 Contract No , 1020 Waterloo, IA CHANGE PROPOSAL REQUEST 1, Double Reinforced PCC Pavement from sta . 152+4076 to Sta . 153+0077 Item Description Quantity Unit Unit Price Total PCC Pavement, 10" (Double Reinforced) 362.1 SY $ 150.50 $ 54,496.D5 TOTAL AMOUNT $ 54,496.05 Notes: *Subbase by others within +-1/10th ft. Joe Owen 319-290-4312 I ® CHANGE ORDER Distribution: HRGreen Owner X Engineer X HR Green , Inc. Contractor X 8710 Earhart Lane S.W. Field Cedar Rapids, IA 52404 (319) 841 -4000 FAX (319)841 -4012 Other Change Order No. 05 PROJECT: Waterloo, IA Shaulis Road Reconstruction — Hess Road to US-218 Date September 28, 2021 To Contractor: Project No. 190428.04 Peterson Contractors, Inc. 104 Black Hawk Street Reinbeck, IA 50669 Original Contract Date May 17, 2021 This Change Order includes the following: (i) Doubled Reinforced PCC Paving The original Contract Sum was $83658,973.95 Net change by previouslyauthorized Change Orders $0.00 The Contract Sum prior to this Change Order was $8,6583973.95 The Contract Sum will be increased by this Change Order in the amount of $8,718,919.61 The new Contract Sum including this Change order will be $8,718,919.61 The Contract Time will be increased b $59,945.66 The date of Substantial Completion letion as of the date of this Change Order therefore is September 21 , 2021 The date of Final Completion as of the date of this Change Order therefore is September 15, 2023 NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE, if applicable, AND OWNER Contractor Owner's Representative Owner Peterson Contractors Inc. HR Green, Inc. City of Waterloo, IA By By o Fieshner �w e,„�,o BY BY BY 9 -2s -21 Date: Date: Date: Date: