CHANGE ORDER NO. 1
CONTRACTOR: Blackhawk Roofing Company PROJECT: FY2021 Young Arena Southeast and
619 E. 19th Street Southwest Roof Replacement Project
Cedar Falls, Iowa 50613 Contract No. 1040
125 Commercial Street
Waterloo, Iowa 50703
OWNER: City of Waterloo PROJECT NO: 20WATWATER003C
Waterloo Leisure Services
1101 Campbell Avenue
Waterloo, Iowa 50703
THE CONTRACT SHALL BE CHANGED AS FOLLOWS:
1. Total tear off of all insulation down to the metal deck and replace with R-30 polyisocyanurate tapered
insulation, add $46,029.00
2. Difference of bid allowance (960 board feet)versus replaced to date (2,413 board feet)at$1.00 per board
foot, add $1,453.00
3. Seven core cuts (2'x 2') performed on Monday, October 4, 2021 by Blackhawk Roofing, add $879.00
JUSTIFICATION:
1. On Thursday, September 30, 2021, Blackhawk Roofing had already replaced 2,413 board feet of wet
insulation. The bid allowance was 960 board feet. It was determined that Travis Nichols, City of Waterloo,
would perform multiple core cuts with Chance Dill, Blackhawk Roofing, on Monday, October 4, 2021. All
seven core cuts taken were wet. It was decided that total tear off of the insulation down to the metal deck
was necessary. Blackhawk Roofing has the insulation in stock at their warehouse. See attached Change
Order Request from Blackhawk Roofing.
ORIGINAL CONTRACT SUM $116,400.00
PREVIOUS CHANGE ORDERS $0.00
CURRENT CONTRACT SUM $116,400.00
THIS CHANGE ORDER $48,361.00
NEW CONTRACT SUM $164,761.00
SCHEDULE CHANGE IN CALENDAR DAYS Unknown
OWNER: CONSULTANT CONTRACTOR:
Jason Hackman, RRO Mike Kerker
City of Waterloo Benchmark, Inc. Blackhawk Roofing
DATE: 10/18/2021 DATE: October 4, 2021 DATE: 10/4/21
6065 Huntington Court NE Cedar Rapids, IA 52402 319.393.9100 319.393.3994 benchmark-inc.com
2110 Pewaukee Road,Suite D Waukesha,WI 53188 319.393.9100 262.549.1308
CHANGE ORDER REQUEST
3
BLACK HAWK
Date: ROOF COMPANY
10/4/2021 619 East 19th Street
Cedar Falls,IA 50613
Project: P.319-277-9355
Young Arena Reroof 2021
Owner Representative Contractor
Benchmark Black Hawk Roof Co., Inc.
The Original Contract Sum $116,400.00
Net Change By Previously Authorized Change Orders $0.00
Change By This Change Order(Add) $48,361.00
Contract Sum To Date Including This Change Order $164,761.00
List of Additional Work Covered Under This Change Order Request
1 Wet Insulation replace 9/28&9/29(2,413 BF) $1,453.00
2 Core cuts with Travis 10/4/21 $879.00
3 Tear off existing insulation down to metal deck and replace with new $46,029.00
R-30.2 average polyisocynaurate
Contractor Owner
By By
Print Name Mike Kerker Print Name
Date Date