Loading...
HomeMy WebLinkAboutWRH, CO #4 - Cont. No. 1021 - 11.1.21 p 1 o;! 1 $m1 STRANDASSOC[ATE ® Strand Associates, Inc 910 West W ingm Drive °r Madison,WI 53715 EXCELLENCE IN ENGINEERING (P)668.251.4843 October 14,2021 CHANGE ORDER NO. 4 PROJECT: FY 2020 Wastewater Treatment Plant Digester No. 3 Cover Modifications OWNER: City of Waterloo,Iowa CONTRACT: 1021 CONTRACTOR: WRH,Inc. Description of Change 4a Adjust Allowance for Draft Tube Mixer Rehabilitation— (DEDUCT) ($360.00) Bearing Replacement from$78,958 to $78,598 in accordance with CAR No. 6 dated November 18,2020. 4b Reimbursement for damage to Insulating PRV/Flame (DEDUCT) ($1,388.59) Arrestor Jacket which occurred during construction in accordance with CAR No. 10 dated September 20,2021,and revised based on the final invoice for replacement dated October 13,2021. Contractor is responsible for 50 percent of the cost. TOTAL VALUE OF THIS CHANGE ORDER: (DEDUCT) ($1,748.59) Contract Price Adjustment Original Contract Price $867,500.00 Previous Change Order Adjustments $45,376.50 Adjustment in Contract Price this Change Order ($1,748.59) Current Contract Price including this Change Order $911,127.91 Contract Substantial Completion Date Adjustment Original Contract Substantial Completion Date October 14,2020 Contract Substantial Completion Date Adjustments due to previous Change Orders 78 Days Contract Substantial Completion Date Adjustments due to this Change Order 274 Days Current Substantial Contract Completion Dates including all Change Orders October 1,2021 Contract Final Completion Date Adjustment Original Contract Final Completion Date November 13,2020 Contract Final Completion Date Adjustments due to previous Change Orders 199 Days Contract Final Completion Date Adjustments due to this Change Order 154 Days Current Final Contract Completion Dates including all Change Orders November 1,2021 SKH:tll\S:\MAD\4400--4499\4463\008\Construction\Change Orders\CO 4\CO 4.docx Arizona j Illinois I Indiana I Kentucky I Ohio I Texas I Wisconsin www.strand.com Strand Associates, Inc.' City of Waterloo—WRH, Inc. Contract 1021, Change Order No.4 Page 2 October 14, 2021 This document shall become a supplement to the Contract and all provisions will apply hereto. RECOM ENDED ✓� 10/14/2021 ENGINEER—Strand Associ tes,Inc.® Date APPROVED CONTRACTOR—WRH, Inc. Date APPROVED Gz�e11 ;11 Hlr-I- 11/1/2021 OWNER—City of Waterloo,Iowa Date SKH:tll\S:\MAD\4400-4499\4463\008\Construction\Change Orders\CO 4\CO 4.docx www.strand.com NYW Change Authorization Request (CAR) Project: City of Waterloo FY 2020 Wastewater Treatment Plant Digester No.3 Cover Modifications CAR No. 10 Insulating Jacket Replacement. DATE September 20,2021 WRH Job No. 1350 Reference: Contract No. 1021 RFQ# Replace Damaged Insulating Jacket Location Digester No.3 Interior Wall A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this authorization is requested so that the material may be purchased and to prevent any delay in field operations. Reason for Change: ( ) Design Request ( X ) Field Condition ( ) Owner Request ( ) Suggested by Contractor ( X ) Other Damaged insulating jacked 1) Description of Change: (Refer to drawings,specification,addenda,bulletin if applicable) Replacement of the Insulating Jacket Cost to replace the Insulating Jacket ($1,413.20) 2) It is requested that the completion date be;(X)extended / ( )reduced by 0 calendar days 3) Bases of Payment: a) ( x ) Firm price for performing this change along with attached supporting details is( )increased / (X)decreased by -$1,413.20 b) ( ) Time and Material per Contract. $0.00 c) ( ) Change to be performed per unit prices in Contract $0.00 d) ( ) The time required to prepare and agree upon a detailed estimate prior to proceeding with the change would unduly delay job progress. The following is an approximate estimate to assist Owner in determining whether or not change should be made. If notified to proceed, a detailed estimate in the form agreed upon,with supporting details,will be submitted after receipt of said notice. Approximate Estimate is: $0.00 FOR OWNER'S ( ) CHANGE WILL NOT BE MADE PROCEED ON THE FOLLOWING BASIS: ( ) Firm Price ( ) Time and Material ( ) Estimate of Price ( ) Change in Completion Date ( ) Unit Price in Contract ( ) No Change Comments: Submitted by: t4,X"V"6". Approved by Project Manager Owner WRH, Inc. F�C`'\GN Date: 9/20/2021 Date: F� N Engineered Equipment Solutions, Inc Invoice 203 E Main St State Center, IA 50247 Date Invoice# 10/13/2021 19-1214 Bill To Ship To City of Waterloo WMS 3505 Easton Ave. Waterloo,IA 50702 P.O. Number Terms Due Date Rep Ship Via Project WP22068 Net 15 10/28/2021 J.S. 10/8/2021 Best Way Quantity Item Code Description Price Each Amount 1 Insulating Jacket VB05.1185.144 2.726.40 2,726.40 Insulating Jacket for a 581013/581 IB Relief Valve& Flame Arrestor Assembly 6" 1 Freight-I shipping 50.77 50.77 �m r f xrtnar Trotw Be9iv>I.vi inn to Zn. .. Total $2,777.17 203 E.Main St.,P.O. Box 541 •State Center,IA 50247• Payments $0.00 Ph. 641.483.2904 •FAX 888.421.2856 www.e-equipmentsolutions.com Balance Due $2'777.17