HomeMy WebLinkAboutCardinal Construction - CO#23 - Five Sullivan Bros. Addition and Reno Project - 11.15.2021 - Document G701 - 2017
Change Order
PROJECT: (Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION:
Five Sullivan Brothers Convention Center Contract For:General Construction Change Order Number:023
Addition and Renovation,Waterloo,IA. Project No:20-23943
Date:September 08,2020 Date:October 20,2021
OWNER:(1llaine and address) ARCHITECT:(Name and address) CONTRACTOR:(Name and address)
City of Waterloo I&S Group,Inc.(ISG) Cardinal Construction,Inc.
715 Mulberry Street 314 East 4th Street 1246 Martin Road
Waterloo,IA 50703 Waterloo,IA 50703 Waterloo,IA 50701
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and,if applicable,attach or reference specific exhibits.Also include agreed upon adjustments
attributable to executed Construction Change Directives)
A. COR 17: Angle Bracing Modification: Remove existing angle braces in Corridor 102 that
cross the corridor and conflict with new mechanical and electrical...........................................Add $1,780.00
TOTAL AMOUNT OF THIS CHANGE ORDER,ADD TO CONTRACT SUM$1,780.00.
The original Contract Sum was $ _5,516,300.00
The net change by previously authorized Change Orders $ 414,754.30
The Contract Sum prior to this Change Order was $ _5,931,054,30
The Contract Sum will be increased by this Change Order in the amount of $ 1,780.00
The new Contract Stun including this Change Order wilt be $ 5,932,834.30
The Contract Time will be unchanged by zero(0)days.
The new date of Substantial Completion will he August 22,2021.
NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract
Time,that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL.SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER.
I&S Group,Inc.(ISG) �^ Carl Construction,Inc. City of Waterloo
ARCHITECT(Finn name) ZSIGA
TOR(Firm name) OWNER(Firm name)
SIGNATURE E SIGNATURE
Nathan Com tion,Architect Katy Susong,President Quentin Hart,Mayor _
PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE
October 20,2021 October 20,2021 11/15/2021
DATE DATE DATE
AIA Document G701--2017.Copyright Q 1979,1987,2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The"American
Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are registered trademarks and may not be used without permission.This document
was produced by AIA software at 13:26:01 ET on 10120/2021 under Order No.9281462824 which expires on 0711212022,Is not for resale,is licensed for one-time
use only,and may only be used in accordance with the AIA Contract Documentse Terms of Service.To report copyright violations,e-mail copyright@aia.arg.
User Notes: (3139ADA3F)