December 31, 2021
Mr. Brian Bowman
City of Waterloo
3505 Easton Avenue
Waterloo, IA 50702
Re: F.Y. 2020 Wastewater Treatment Plant Biosolids Modifications Project
Contract No. 994
City of Waterloo, Iowa (City)
Dear Brian,
Strand Associates, Inc.®
910 West Wingra Drive
Madison, WI 53715
(P) 608.251.4843
Change Order No. 5 for the Contract with Woodruff Construction related to the above -referenced project
is enclosed. This change order captures several modifications to the original Contract resulting in an
addition of $55,566.00 to the Contract price. In addition, this change order also results in a change to the
completion date of the project because of impacts to the supply chain from COVID-19 in early 2021,
resulting in a delay to the procurement of equipment and construction materials.
As of Woodruff Construction's most recent pay request for the period ending on November 30, 2021,
this project is 88.1 percent complete with 84 percent of the Contract time elapsed. The total value of
changes to the original Contract price are summarized in the following table.
Change Order
Amount
Nos. 1, 2, 3 and 4
ADD
$78,735.10
No. 5
ADD
$55,566.00
Total
ADD
$134,301.10
The current change in the Contract price is 0.8 percent of the original Contract value.
Please call 608-251-4843 if you have any questions.
Sincerely,
STRAND ASSOCIATES, INC.®
Samuel K. Hocevar
Enclosure
SKH:tII\S:\MAD\4400- 4499\4463\009\Constmction\Change Orders\005\CO 5 Cover Letter.docx
Arizona I Illinois I Indiana I Kentucky I Ohio I Texas I Wisconsin www.strand.com
of
EXCELLENCE IN ENGINEERING
December 20, 2021
CHANGE ORDER NO. 5
PROJECT:
OWNER:
CONTRACT:
CONTRACTOR:
heii STRANDASSOCIATE®
Strand Associates, Inc
910 West Wingra Drive
Madison, WI 53715
(P) 608.251.4843
F.Y. 2020 Wastewater Treatment Biosolids Modifications Project
City of Waterloo, Iowa
City Contract No. 994
Woodruff Construction, LLC
Description of Change
5a Provide galvanized plate lintels at the four overhead
door openings in Structure 330 in accordance with the
enclosed cost proposal dated July 26, 2021.
5b Provide gate valve in new 4-inch W2 line in
Structure 170 and gate valve in new 4-inch W2 line in
Structure 190 in accordance with the enclosed Cost
Proposal Request (CPR) 013 dated August 17, 2021.
5c Provide bearing plate for the insulated metal panel at the
far southwest end of Structure 330 in accordance with
the enclosed cost proposal dated October 1, 2021.
5d Provide identification for process interconnections
piping and equipment in accordance with the enclosed
CPR 014 dated August 26, 2021.
5e Provide modifications to storm piping near
Structure 350 in accordance with the enclosed cost
proposal dated September 27, 2021.
5f Provide partial demolition of abandoned tank walls
northwest of Structure 190 in accordance with the
enclosed CPR 016 dated September 7, 2021.
5g Amend Contract Substantial Completion date and
Contract Final Completion date for time lost for
construction material procurement as a result of
COVID-19 impacts on manufacturing and supply
chains
TOTAL VALUE OF THIS CHANGE ORDER: ADD
Contract Price Adjustment
Original Contract Price
Previous Change Order Adjustments
Adjustment in Contract Price this Change Order
Current Contract Price including this Change Order
SKH:II\S:\MAD\4400--4499\4463\009\Construction \Change Orders\005\CO 5.docx
ADD
ADD
ADD
ADD
ADD
ADD
ADD
$6,804.00
$7,855.00
$3,239.00
$21,036.00
$6,961.00
$9,671.00
$0.00
$55,566.00
$16,587,300.00
$78,735.10
$55,566.00
$16,721,601.10
Arizona 1 Illinois I Indiana I Kentucky I Ohio I Texas I Wisconsin
www.strand.com
Strand Associates, Inc.r
City of Waterloo, Iowa —Woodruff Construction, LLC
Contract 994, Change Order No. 5
Page 2
December 20, 2021
Contract Substantial Completion Date Adjustment
Original Contract Substantial Completion Date
Contract Substantial Completion Date Adjustments due to previous Change Orders
Contract Substantial Completion Date Adjustments due to this Change Order
Current Substantial Contract Completion Dates including all Change Orders
Contract Final Completion Date Adjustment
Original Contract Final Completion Date
Contract Final Completion Date Adjustments due to previous Change Orders
Contract Final Completion Date Adjustments due to this Change Order
Current Final Contract Completion Dates including all Change Orders
oitiiii
`. . roN�,f��This document shall
c) •••� •ECOMME IDED
_, : RANDALL A. ' 0::
_ z • WI RTZ m fry
:-. 1E137 . GINEER—Strand Asso es, Inc �u Date
�-j ,
•
January 2, 2022
47 Days
37 Days
March 27, 2022
March 3, 2022
47 Days
37 Days
May 26, 2022
become a supplement to the Contract and all provisions will apply hereto.
CON 2 ACTO €—Woodruff Construction, LLC
APPROVED
OWNER —City of Waterloo, Iowa
SKHaII\S:\MAD\4400-4499\4463\009\Constmction\Change Orders\ 005 \CO 5,docx
i/3'7, Zj
12/21/21
Date
1/18/2022
Date
www.strand.com