HomeMy WebLinkAboutCardinal Construction, Inc. - CO #6 - Convention Center 2nd Floor Renovation - 2.7.2022!AIA Document G701 - 2017
Change Order
PROJECT: (Name and address)
Five Sullivan Brothers Convention Center
2nd Floor Renovation, Waterloo, IA,
OWNER: (Name and address)
City of Waterloo
715 Mulberry Street
Waterloo, IA 50703
CONTRACT INFORMATION:
Contract For: General Construction
Project No: 20-24695
Date: May 26, 2021
ARCHITECT: (Name and address)
I & S Group, Inc. (ISO)
314 East 4th Street
Waterloo, IA 50703
CHANGE ORDER INFORMATION:
Change Order Number: 006
Date: January 20, 2022
CONTRACTOR: (Name and address)
Cardinal Construction, Inc.
1246 Martin Road
Waterloo, IA 50701
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments
attributable to executed Construction Change Directives.)
A. COR 07: Cost for Sprinkler Valve. Assembly Update Add $18,751.00
TOTAL AMOUNT OF THIS CHANGE ORDER, ADD TO CONTRACT SUM $18,751.00.
The original Contract Sum was
The net change by previously authorized Change Orders
The Contract Sum prior to this Change Order was
The Contract Sum will be increased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
The Contract Time will be unchanged by Zero (0) days.
The new date of Substantial Completion will be December 23, 2021; New Final Completion Date: January 7, 2022.
$ 1,810,800.00
$ 24,940.00
$ 1,835,740.00
$ 18,751.00
$ 1,854,491.00
NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract
Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
I & S Group, Inc. (1SG)
ARCHITECT (Firer name)
SIGNATURE
Nathan Compton, Architect/Project
Manager
C
CO
onstruction, Inc.
CTOR (Finn name)
City of Waterloo
OWNER (Firm name)
SIGNA URE SIGNATURE
Katy Susong, President Quentin Hart, Mayor
PRINTED NAME AND TITLE PRINTED NAME AND TITLE
January 20, 2022 January 24, 2022
DATE
DATE
PRINTED NAME AND TITLE
2/7/2022
DATE
AIA Document G701' — 2017. Copyright 01979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. The "American
Institute of Architects," "AIA," the AIA Logo, and "AIA Contract Docun:enls" are registered trademarks and may not be used without permission. This document
was produced by AIA software at 14:02:43 CT on 01/20/2022 under Order No.9281462824 which expires on 07/1212022, is not for resale, is licensed for one-
time use only, and may only be used in accordance with the AIA Contract 13ocumentso Terms of Service. To report copyright violations, e-mail
copyright aia.otg.
User Notes: (3B9ARA3F)