Re: FY 2021 Leversee Road Lift Station
Waterloo, Iowa
City Contract No. 983
CGA PN 5623 1.06
Dear Matt:
CGA
ENGINEERS • LAND SURVEYORS
Enclosed electronically for your review and processing is one (1) copy of Change Order #01
prepared on the City of Waterloo's standard form for the above referenced project. A full,
summarized change order request has not been submitted by Arends Excavating at this time.
CGA recommends executing the enclosed change order based on the below summary:
• Add bollards around the generator: $10,044.02
• Add signage around the generator: $471.50
• Add fire extinguisher and signage: $633.08
• Change electrical panel to NEMA 12: $2,551.85
• Add additional conduit to separate circuits $5,664.46
Subtotal of changes is $19,364.91. A ten percent markup for the Prune Contractor has been
added per SUDAS Standard Specifications Section 1090 Subsection 1.04 to rcach a total of
$21,301.40 as shown on the attached copy of Change Order #01.
Please return one (1) executed copy of the signed change order to our office for our file. Please
contact CGA at your earliest convenience if you have any questions on the information provided.
Sincerely,
CLAPSADDLE-GARBER ASSOCIATES, IN
Lary Koosmann, EI, LSI
Project Manager
Clapsaddle-Garber Associates, Inc.
16 East Main Street • Marshalltown, Iowa 50158 • Telephone 641-752-6701 • Fax 641-752-2849
Toll Free 800-542-7981 • www.cgaconsultants.com
CITY OF WATERLOO, IOWA
CHANGE ORDER NO.1
PROJECT: FY 2021 Leversee Road Lift Station, CONTRACT NO. 983
Date Prepared: 11/1312021 AMOUNT: Increase $21,301.40
TO: Arends Excavating , Contractor
You are hereby ordered to make the following changes from the plans and specifications or perform
the following extra work on your contract dated 12/28/2020.
A. Description of change to be made or extra work to be done:
Add Item CO 1,1: Generator Bollards
Add Item CO 1.2: Generator Signage
Add Item CO 1.3: Fire Extinguisher and Signage
Add Item CO 1.4: Change Panel Rating to Nema 12
Add Item CO 1.5: Additional Conduit to Separate Circuits
B. Reason for ordering change or extra work:
Fuel tank permitting requires additional items including bollards, signage and fire
extinguisher. Panel schedule required correction.
C. Settlement for cost of work to be made as follows:
Add Item CO 1.1: Generator Bollards
Add Item CO 1.2: Generator Signage
Add Item CO 1,3: Fire Extinguisher and Signage
Add Item CO 1.4: Change Panel Rating to Nema 12
Add Item CO 1.5: Additional Conduit to Separate Circuits
CITY OF WATERLOO
BY:
4/4/2022
Mayor Date
ATTEST:
City Clerk Date
Total Net Increase $21,301.40