HomeMy WebLinkAboutWRH - Change Order No. 11, Contract No. 907 - 5.2.2022Owner City of Waterloo
FINAL QUAFTITh)ADJUSTMENT
Date: 4/18/2022
Project Satellite Wet Well Rehabilitation
Owner's Contract No. 907
Date of Contact Start 9/17/2018
Contractor:
Contract Amount:
WREI, Inc.
$ 1,839,380.00
You are directed to make the following changes In the Contract Documents. Description:
11 Satellite Grout
12 Satellite Repair
TOTAL DEDUCTIONS
$ 1,100.00 /GAL
$ 230.00 /CF
-75 GAL $ (82,500.00)
-7.26 CF $ (1,670.00)
$ (84,170.00)
Reason for Change Order
11 Removed from contract.
12 Reduction In completed quantity.
CONTRACT PRICE
Original:
Previous C.O.s (ADD/DEDUCT)
This C.O. (ADD/DEDUCT)
Contract Price with all approved Change Orders:
$ 1,839,380.00
$ 417,034.00
$ (84,170.00)
$ 2,172,244.00
Original Completion Date:
Revised Completion Date:
CONTRACT TIME
To Substantial To Final
Completion Completion
11/20/20201 12/18/2020
3/31/2022
it Is agreed by the Contractor that this Change Order Includes any and all costs associated with or resulting from the change(s) ordered herein,
Including all Impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of thls Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPROVED}. �
BY: `—'�} LX,A.J.SZ�'vc
Owner (Authorized Signature)
ACCEPTED
BY:
Mitchell Vargson mn„,,,;5115,0,
Contractor (Aulhorized Signature)
ACCEPTED:
BY:
AECOM
Date
4/18/22
Dale
4/18/2022
Date
AECOM
60488465/606093771
Project No. Final Qty Adj