Change Order
Document G701,' — 2017
PROJECT: (Name and address)
City of Waterloo Sullivan Brothers Plan
Renovation, Wait; tau, IA,
OWNER: (Nume and ad(1 s,$)
City or Waterton
715 Mulberry Street
Waterloo, TA 50703
CONTRACT INFORMATION:
Contract For: General Construction
Project No: 21-25083
Date: February 24, 2022
ARCHITECT: (Nacre and address)
I & S Group, Inc. USG)
314 East 4th Street
Waterloo, 1A 50703
CHANGE ORDER INFORMATION:
Change Order Number: 001
Date: June 3, 2022
CONTRACTOR: (Name and address)
Vieth Construction Corporation
6419 Nordic Drive
Cedar halts, IA 50613
THE CONTRACT'S CHANGED AS FOLLOWS:
Omen a detailed cls aarljtfion of `lhcrchange and, if nppfianbk, ouch ur rcclhreneet speelJie exhibits. Also include agreed upon arlfustirrenrs
ullrlhrilnhle io esec,wti d Ca, 1rnelion Change Dim:lives;)
A. TO runtish and install MasterSeal Traffic 2500 Light Duty System: proper prep of existing
txltict'cic•shalt tlitd joints, install MasterSeal M 270 baseeoat (waterproofing rnetttbraue) and
install MasterScal TC 295 (UV stable). All work to be completed in one mobilization Add $24,950.00
REDUCE SPECIFIED EXI4.)X'Y COATING ALLOWANCE FROM S80,000.00 TO S55,050.00.
CONTRACT SLIM REMAINS UNCHANGED.
The original Caatrnet Sum wits
The net cllunge:by previously authorized Change Riders
The Contract Suitt prior to this Change Order was
The Contract Sum will be unchanged by this Change Order in the amount of
The new Contract Sum including this Change Order will be
The Contract Time will be nnehanged by Zero (0) days.
The new date of Substantial Completion will be September 2, 2022 (per Addenda fit).
$ _...1.,692,500.000
$ 0.00
$ 1,692,500.00
0.00
$ 1,692,500.00
NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract
Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
()water and (,nitti'actor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
T Sr. 5 Group, Inc. (1SGI
Vieth C onstnrctiort Corporation City of Waterloo
ARCHITECT (Firm name) CONT (l•'trrrr nftcc�.'
SIGNATURE SIGNATUR SIGNATURE
'Cony Vieth, President Quentin Hart, Mayor
OWNER (Lr r anal
Querrtui 9 tar
Nathan Compton, Architect/Project
Maltpger.
PRINTED NAME AND TITLE
June 3, 2022
DATE
PRINTED NA AN TITLE
PRINTED NAME AND TITLE
June 20, 2022
DATE DATE
AIA Document G701" — 2017. Copyright 01979, 1987, 2000 , 2001 and 2017 by The Aniertcan Institute of Architects. At tights reserved. The "Arnericar
Institute nt Architects," "AIA,' ILe AIA Logo, anti 'AIA [ onVact Documents' are registered tradema'ks and may not be users will r,ut preinission. This document
was produced by AIA software at 11:36:24 CT on 06/03/2022 under Order No.9281462824 which expires on 07 12/2022, is not for resale, is licensed far one-
time use only, and may only be used in accordance with the AIA Contract Documents°° Terms of Service. To report copyright vialaltons, e-mail
copyrightrryaia.org.
User Notes: (369AFJA48)