CHANGE or EXTRA WORK ORDER NO. 03
PROJECT: F.Y. 2022 SIDEWALK REPAIR PROGRAM CONTRACT NO. 1061
Date Prepared:
August 23, 2022 AMOUNT: $30,336.0 INCREASE
TO: BROCK EVEN CONSTRUCTION , Contractor
You are hereby ordered to make the following changes from the plans and specifications or perform the
following extra work on your contract dated JUNE 06, 2022
A. Description of change to be made or extra work to be done:
3001 Remove Sidewalk
3002 Sidewalk, PCC, 6"
3003 Traffic Control
B. Reason for ordering change or extra work:
Sidewalk work covered under this change order includes trail repairs for the Shaulis Road Trail.
The City is electing to have the trail repairs made by the City's Sidewalk repair contractor and
paid under a new division (Division 7) through a separate funding source.
C. Settlement for cost of work to be made as follows:
Item
No.
Item Description
Engr. Est.
Quantities
Units
Engr. Est.
Unit Price
Engr. Est. Total
Cost
3001
Remove Sidewalk
2,520.0
SF
$ 3.60
$ 9,072.00
3002
Sidewalk, PCC, 6"
2,520.0
SF
$ 8.20
$ 20,664.00
3003
Traffic Control
1.0
LS
$ 600.00
$ 600.00
TOTAL INCREASE
$ 30,336.00
�uz to lb. t sioeEu 9/6/2022
BY: BROCK EVEN, INC
Mayor
ATTEST:
Kerrey Fe[chfe
Date
CONTRACTOR
BY:
2.S'- 22
Date
9/6/2022 TITLE:
City Clerk
Date APPROVED:
ty Engine- ate
Change Order No. 03