HomeMy WebLinkAboutCardinal Construction CO #34 - 5 Sullivan Bros CC and Renovation Project - 9.19.2022SAIA Document G701 - 2017 Change Order PROJECT: (Name and address) Five Sullivan Brothers Convention Center Addition and Renovation, Waterloo, IA. OWNER: (Name and address) City of Waterloo 715 Mulberry Street Waterloo, IA 50703 CONTRACT INFORMATION: Contract For: General Construction Project No: 20-23943 Date: September 08, 2020 ARCHITECT: (Name and address) I & S Group, Inc. (ISG) 314 East 4th Street Waterloo, IA 50703 CHANGE ORDER INFORMATION: Change Order Number: 034 Date: August 25, 2022 CONTRACTOR: (Name and address) Cardinal Construction, Inc. 1246 Martin Road Waterloo, IA 50701 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments attributable to executed Construction Change Directives.) A. COR 24: Elevator Reinspection - Phone line for elevator was installed but at the time of inspection there was no dial tone at the elevator and it was determined that there was no dial tone at the termination point shown Add $6,307.00 TOTAL AMOUNT OF THIS CHANGE ORDER, ADD TO CONTRACT SUM $6,307.00. The original Contract Sum was The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be increased by this Change Order in the amount of The new Contract Sum including this Change Order will be The Contract Time will be unchanged by Zero (0) days. The new date of Substantial Completion will be August 22, 2021. $ 5,516,300.00 $ 457,770.30 $ 5,974,070.30 $ 6,307.00 $ 5,980,377.30 NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. I & S Group, Inc. (ISG) ARCHITECT (Firm name) SIGNATURE Nathan Compton, Architect PRINTED NAME AND TITLE August 25, 2022 DATE dinal Construction Inc. SI ` ' TURE Katy Susong, President PRINTED NAME AND TITLE August 29, 2022 DATE City of Waterloo OWNER (Firm name) 1 1Zuenti, d1art SIGNED SIGNATURE Quentin Hart, Mayor PRINTED NAME AND TITLE 9/19/2022 DATE AIA Document G701 ' — 2017. Copyright © 1979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 13:54;17 CT on 08/25/2022 under Order No.2114332387 which expires on 07/12/2023, is not for resale, is licensed for one- time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (3B9ADA46)