HomeMy WebLinkAboutLangman Construction - Hwy 63 Sanitary Sewer UPgrades - CO #2 - 11.7.2022CHANGE ORDER NO. 02
Owner: City of Waterloo Date October 28, 2022
Project: US Highway 63 Sanitary Sewer Upgrades, Phase I
Owner's Contract No.: City Contract No. 1037 Contractor: Langman Construction, Inc.
Date of Contract Start: October 18, 2021 $ Original Contract: $7,190,038.90
You are directed to make the following changes in the Contract Documents. Description:
Additions:
• Connection to Existing Sanitary Manhole = $10,000.00
• 8-Inch Sanitary Sewer Gravity Main (106.5 LF) — Open Cut = $13,814.94
• Tree Removal = $2,339.84
• 8-Inch Internal Drop Connection = $2,670.73
• Planting of Three (3) Colorado Blue Spruce (5'-6' Height), No Watering = $2,760.00
TOTAL ADDITIONS: $31,585.51
TOTAL DEDUCTIONS: ($0.00)
NET CHANGE ORDER AMOUNT: $31,585.51
Reason for Change Order:
An unknown house service was found during construction in the in the Home Park area which ties into an existing manhole, intended to be abandoned
as part of this project. The manhole needed to be altered to accommodate the service and tie into the new 48-inch line. This connection also required
an additional 8-inch line, drop connection, and connection to a new manhole. It was necessary, as part of the installation of the 8-inch connection, to
remove three trees and one bush, and plant three replacement trees.
CONTRACT PRICE
Original: $ 7,190,038.90 Original:
Previous C.O.s (ADD/DEDUCT): $ (380,516.00) Previous C.O.s (ADD/DEDUCT):
This C.O. (ADD/DEDUCT): $ 31,585.51 This C.O. (ADD/DEDUCT):
Contract Price With All Approved
Change Orders: $ 6,841,108.41 REVISED:
Original Completion Date:
Revised Completion Date:
CONTRACT TIMES (Calendar Days)
To Substantial To Final
Completion Completion
Nov. 18, 2022
28
3
Nov. 18, 2022
Dec. 21, 2022
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays,
and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
APPROVED.
entin ITart
By:
11 /7/2022
City of Waterloo (Authorized Signature) Date:
ACCEPTED:
By:
10/28/2022
Langman Construction, Inc. (Authorized Signature) Date:
AECOM
60651387/60671367 02
Project No. Change Order No.
Page 1 of 1
• :\DCS\Projects\WTR\60671367_63_S_ Interceptor Ph I_CRS\600_Construction_Support\660_Change_Orders\CO#02\LangmanConst_CO2-10.28.2022.doc