HomeMy WebLinkAboutCedar_Valley_Corporation_CO #3 - Taxi Bravo - 11.21.2022CHANGE ORDER NO. 3 Owner: Waterloo Regional Airport, City of Waterloo, Iowa Date: August 9, 2022 Project: Reconstruct West Terminal Apron & Clean/Reseal Joints East Terminal Apron, Reconstruct Taxiway B East of Runway 18/36 and Tree Removals Reconstruct Taxiway C South of Runway 12/30 Runway Safety Area Owner's Contract No. FAA AIP Project No. 3-19-0094-046 Contractor: Cedar Valley Construction Co. LLC Date of Contract Start: April 6, 2021 You are directed to make the following changes in the Contract Documents. Description: Item No. Description Unit Unit Price Quantity Amount BID PACKAGE #1 - RECONSTRUCT WEST TERMINAL APRON AND CLEAN/RESEAL JOINTS EAST TERMINAL APRON 4 PAVEMENT REMOVAL SY $ 6.50 40.0 $ 260.00 5 REMOVAL OF STRUCTURE EA $ 1,500.00 2.0 $ 3,000.00 6 UNCLASSIFIED EXCAVATION CY $ 12.00 20.0 $ 240.00 7 SUBBASE COURSE CY $ 62.50 (260.0) $ (16,250.00) 8 CRUSHED AGGREGATE BASE COURSE - 6 INCH SY $ 20.00 40.0 $ 800.00 9 CEMENT -TREATED PERMEABLE BASE COURSE SY $ 28.98 960.0 $ 27,820.80 10 10.0-INCH PORTLAND CEMENT CONCRETE PAVEMENT SY $ 82.48 40.0 $ 3,299.20 12 RUNWAY AND TAXIWAY MARKING SF $ 5.50 (20.0) $ (110.00) 19 CATCH BASIN, ADJUSTMENT EA $ 9,500.00 (0.9) $ (8,550.00) ADD ALTERNATE BID 2 SAW AND SEAL JOINTS LFT $ 3.40 115.0 $ 391.00 4 CONSTRUCTION BARRICADES LS $ 25,000.00 (0.15) $ (3,750.00) 5 INSTALLATION AND REMOVAL OF SILT FENCE LF $ 1.75 (755.0) $ (1,321.25) 13 CRUSHED AGGREGATE BASE - 6-INCH SY $ 20.00 (87.0) $ (1,740.00) 14 CEMENT -TREATED PERMEABLE BASE COURSE SY $ 26.32 (240.0) $ (6,316.80) 15 8.0-INCH PORTLAND CONCRETE CEMENT PAVEMENT SY $ 88.04 77.7 $ 6,840.71 16 13.0-INCH PORTLAND CONCRETE CEMENT PAVEMENT SY $ 72.40 (28.9) $ (2,092.36) 17 RUNWAY AND TAXIWAY MARKING SF $ 5.50 (334.0) $ (1,837.00) 19 6 - INCH PERFORATED SUBDRAIN (SDR 35) COMPLETE INCLUDING POROUS BACKFILL AND FILTER FABRIC LFT $ 14.00 (160.0) $ (2,240.00) L 20 6 - INCH NON -PERFORATED SUBDRAIN (SDR 35) LFT $ 8.50 (25.0) $ (212.50) 23 SEEDING AC $ 900.00 (7.3) $ (6,570.00) ALO FAA AIP 3-19-0094-046 CO-3 Project No - 60642636 1 25 MULCHING AC $ 1,825.00 (7.3) $ (13,322.50) 26 NO. 8 AWG, 5KV, L-824, TYPE C CABLE, INSTALLED IN TRENCH, DUCT BANK OR CONDUIT LF $ 1.00 3,150.0 $ 3,150.00 27 NO. 6 AWG, 5KV, L-824, TYPE C CABLE, INSTALLED IN TRENCH, DUCTBANK OR CONDUIT. LF $ 1.25 (15.0) $ (18.75) 28 NO. 6 AWG, BARE COPPER COUNTERPOISE WIRE, INSTALLED IN TRENCH, ABOVE THE DUCT BANK OR CONDUIT, INCLUDING GROUND RODS AND GROUND CONNECTORS LF $ 0.85 (758.0) $ (644.30) 29 CONCRETE ENCASED ELECTRICAL DUCT BACK, 4-WAY, 4-INCH SCHEDULE 40 PVC LF $ 38.00 65.0 $ 2,470.00 30 NON -ENCASED ELECTRICAL CONDUIT, 2-INCH SCHEDULE 40 PVC LF $ 2.10 470.0 $ 987.00 31 ELECTRICAL HANDHOLE, L-868 EA $ 900.00 (2.0) $ (1,800.00) 34 AIRFIELD GUIDANCE SIGN, SIZE 1, LED, 1 (ONE) MODULE EA $ 2,400.00 (1.0) $ (2,400.00) 36 AIRFIELD GUIDANCE SIGN, SIZE 3, LED, 1 (ONE) MODULE EA $ 2,670.00 (1.0) $ (2,670.00) 37 AIRFIELD GUIDANCE SIGN, SIZE 3, LED, 1 (THREE) MODULE EA $ 3,275.00 1.0 $ 3,275.00 39 REMOVE DUCT BANK LF $ 7.00 (700.0) $ (4,900.00) 40 REMOVE TAXIWAY EDGE LIGHT EA $ 255.00 15.0 $ 3,825.00 41 REMOVE ELECTRICAL HANDHOLE EA $ 258.00 (1.0) $ (258.00) 43 ASPHALT SURFACE COURSE TON $ 640.00 8.0 $ 5,120.00 45 10" CLASS HI, REINFORCED CONCRETE PIPE LF $ 65.00 (8.0) $ (520.00) 101 PARTIAL DEPTH PATCHING, FINISHED SF $ 110.00 13.0 $ 1,430.00 201 TAXIWAY EDGE LIGHT COVERS EA $ 55.00 20.0 $ 1,100.00 202 ASOS CABLE SPLICE EA $ 687.50 1.0 $ 687.50 203 AIRFIELD GUIDANCE SIGN, SIZE 1, LED, 3 (THREE) MODULE EA $ 3,275.00 2.0 $ 6,550.00 204 AIRFIELD GUIDANCE SIGN, SIZE 3, LED, 2 (TWO) MODULE EA $ 4,050.00 1.0 $ 4,050.00 205 DELETE PAINTED CLOSED RUNWAY MARKERS (RUNWAY 6/24) SFT $ 1.08 (3,476.0) $ (3,754.08) 206 DELETE MOBILIZATION FOR PAINTED CLOSED RUNWAY MARKERS (RUNWAY 6/24) EA $ 500.00 (1.0) $ (500.00) 207 MOBILIZATION FOR PAINT REMOVAL EA $ 1,500.00 2.0 $ 3,000.00 208 PAINT REMOVAL SFT $ 1.50 3,854.0 $ 5,781.00 209 PAINT REMOVAL TRUCK STANDBY HRS $ 937.50 4.0 $ 3,750.00 210 REPLACE MANHOLE COVER WITH GRATE EA $ 741.00 1.0 $ 741.00 211 POWER FOR LIGHTED Xs PROVIDED BY AIRPORT (CREDIT FOR FUEL, FUELING & MAINTENACE OF DIESEL ENGINES) GAL $ 3.50 (411.4) $ (1,439.90) TOTALS $ 5,350.77 ALO FAA AIP 3-19-0094-046 CO-3 Project No - 60642636 2 Reason for Change Order: Items 1 through 101 - Plan quantities have been adjusted to reflect actual field measurements. Item 201 — Item added to allow for daytime only use of the section of Taxiway B west of Runway 18/36. Item 202 — Item added to repair damage ASOS Cable that was identified to be encased in concrete. Items 203 & 204 — Items added to reflect shop drawing submittals for guidance signs. Item 205 & 206 — Item added to reflect that Runway 6/24 Closure Markers were installed by Owner Funded Project and Runway was closed prior to Notice to Proceed for this project. Item 207, 208 & 209 — Items added to allow for additional paint removals for the project. Item 210 — Item added to allow for change of a solid manhole lid on the adjacent general aviation apron with a grated intake lid. Item 211 — Item added to provide credit for fuel not used related to the Lighted Closed Runway Markers. Lighted Closed Runway Markers were powered from existing electrical services on the airfield. Total change Items 1 through 101 Total change Items 201 to 211 Total change Items 1 through 211 ALO FAA AIP 3-19-0094-046 $ (14,614.75) $ 19.965.52 $ 5,350.77 CO-3 Project No — 60642636 3 CONTRACT PRICE Original: $ 4,116,725.00 Previous C.O.s ADD: $ 349,420.00 This C.O. (ADD): $ 5.350.77 Liquidated Damages: $ (16,500.00) (33 Days @ $500/Day) Contract Price with all approved Change Orders: $ 4,454,995.77 CONTRACT TIMES (Calendar Days) To substantial To final completion completion Original: Previous C.O.s (ADD): This C.O. (ADD): REVISED: 150 4 5 159 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. RECOMMENDED: By:` -- Engineer (Authorized Signature) APPROVED: QuertEaz »aarf By: Owner (Authorized Signature) ACCEjI'E By: hi Contractor (Authorized Signature) August 27, 2022 Date 11 /21 /2022 Date ZZ Zo z2 Date ALO FAA AIP 3-19-0094-046 CO-3 Project No — 60642636 4