HomeMy WebLinkAbout2023-069-02.06.2023Prepared by LeAnn M. Even, Deputy City Clerk, City of Waterloo, 715 Mulberry Street, Waterloo,
IA 50703, 319-291-4323.
RESOLUTION NO. 2023-069
RESOLUTION APPROVING THE PARTIAL RELEASE OF
RETAINAGE TO WOODRUFF CONSTRUCTION OF
WATERLOO, IOWA, IN THE AMOUNT OF $767,486.06, WITH
THE EXCEPTION OF THE OUTSTANDING ITEMS WHICH
ARE IMPACTED BY MATERIAL LEAD TIMES OR
WEATHER CONDITIONS, IN CONJUNCTION WITH THE FY
2020 WASTEWATER TREATMENT PLANT BIOSOLIDS
MODIFICATIONS PROJECT, CONTRACT NO. 994.
WHEREAS, Woodruff Construction of Waterloo, Iowa, performed work in conjunction
with the FY 2020 Wastewater Treatment Plant Biosolids Modifications Project, Contract No.
994, and
WHEREAS, Woodruff Construction has completed 99.4% of the aforementioned project,
in accordance with the bid documents, specifications, form of contract, etc., as approved by
Council March 2, 2020, Resolution No. 2020-147.
WHEREAS, the remaining items to close-out the project are impacted by final material
lead times and seasonal conditions and Waste Management Services anticipates final completion
of the remaining items in the spring of 2023.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WATERLOO, IOWA, that the request of Woodruff Construction for a partial release of
retainage, in the amount of $767,486.06, with the exception of the outstanding items which are
impacted by material lead times or weather conditions, in conjunction with the FY 2020
Wastewater Treatment Plant Biosolids Modifications Project, Contract No. 994, is hereby
approved.
PASSED AND ADOPTED this 6th day of February 2023.
ATTEST:
Kelley Felchle
Kelley Felchle, City Clerk
SEAL
0
0
• 11111■111111 11111111
0
Quentin Hart, Mayor