HomeMy WebLinkAboutModern Builders - CO#1 - Hangar No. 4 Renovations - 3.20.2023CHANGE ORDER NO. 1
Owner: Waterloo Regional Airport, City of Waterloo, Iowa
Project: Hangar No. 4 Improvements (2022)
Owner's Contract No. IDOT CSVI Project No. 9I220AL0200
IDOT Contract No. 3345
Contractor: Modern Builders, Inc.
Date of Contract Start: October 11, 2022
Date: March 6, 2023
You are directed to make the following changes in the Contract Documents. Description:
Item
No.
Description
Unit
Unit Price
Quantity
Amount
101
ADA Restroom Modifications
LS
$3,061.30
1
$ 3,061.30
Total Change Order $ 3,061.30
Reason for Change Order:
101 — Access to restroom to be provided by the following items:
Demo stud wall
Create opening in block wall for new doorway
Infill block opening with wood
Install wood door into framed opening (using salvaged door)
Infill old door location with wood
Sheetrock Openings
IDOT Contract No. 3345
CO-1 IDOT CSVI Project No. 9I220AL0200
1
CONTRACT PRICE
Original: $
Previous C.O.s (DEDUCT):$
157,368.00
0.00
This C.O. (ADD): $ 3,061.30
Contract Price with all
approved Change Orders: $ 160,429.30
CONTRACT TIMES (Calendar Days)
To substantial To final
completion completion
Original:
Previous C.O.s (ADD):
This C.O. (ADD):
REVISED:
180
0
0
180
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By: 3 l ±----
Engineer (Authorized Signature)
APPROVED:
Qcter l U� °smxeo
By:
Owner (Authorized Signature)
ACCEPTED:
By:
Contractor (Authorized Signature)
March 7, 2023
Date
3/20/2023
Date
Date
IDOT Contract No. 3345
CO-1 IDOT CSVI Project No. 9I220AL0200