HomeMy WebLinkAboutModern Builders - Hangars 1&2 Roof Repairs - 4.3.2023CONTRACT
FOR
HANGARS 1 & 2 ROOF REPAIRS
FAA AIP 3-19-0094-048 (CARES MNT)
AT THE
WATERLOO REGIONAL AIRPORT
WATERLOO, IOWA
THIS AGREEMENT, made and entered into this u day of Qg-tr. , 20 by and between the Waterloo
Regional Airport for the City of Waterloo, Black Hawk County Iowa hereinafter referred to as the "Owner" and
Modern Builders, Inc. (a corporation organized and existing under the laws of the
rS^tale of Iowa), (a-partnership-eonsisting-ef- )-(art-individual trndiug-as- ) of
,5fie_l?bvi Ije, in the State of nu' i hereinafter referred to as the "Contractor."
WITNESSETH: That the Contractor for and in consideration of Thirty -Three Thousand Nine Hundred Forty -Eight
Dollars ($33 948.00) based on the unit bid prices payable as set forth in the Specifications constituting a part of this
Contract, hereby agrees to construct in accordance with the Plans and Specifications therefore, and in the location
designated on the Plans, the various items of work awarded said Contractor on the day of
, 20 , as follows, being numbered 1 through 4 as shown in schedule of prices bid in the
attached Proposal which is a part of this Contact.
Said Specifications and Plans are hereby made part of and the basisofthis Agreement and a true copy of said Plans and
Specifications is now with the Waterloo Regional Airport in the office of the Director of Aviation, Waterloo, Iowa, under
date of November 17 20 .
1. That in consideration of the foregoing, the Owner hereby agrees to pay the Contractor promptly and according to
the requirements of the Specifications, the amounts set forth, subject to the conditions as set forth in the
Specifications.
2, That it is understood that the parties named herein are the only persons interested in this Contract and principals.
3. That the Contractor has examined the site of the proposed work, Plans, Specifications, and Contract Documents in
order that he might become familiar with the character, quality, and quantity of the work to be performed, the
materials to be fumished and the requirements of the Specifications, and Contract Documents.
4. It is hereby further agreed that any reference herein to the "Contract" shall include all "Contract Documents" for
the Waterloo Regional Airport, FAA Project Nos. 3-19-0094-048 Hangars 1 Sc 2 Roof Repairs and said "Contact
Documents" are hereby made a part of this agreement as fully as if set out at length herein, and that this contract is
limited to the items in the proposal as signed by the "Contractor" and included in the "Contract Documents."
5. That in the event any surety upon any bond furnished in connection with this Contract becomes unacceptable to the
Owner, or limy such surety shall fail to furnish reports as to his financial condition from time to time as requested
by the Owner, the Contractor agrees to furnish promptly such additional security as may be required from time to
time to protect the interests of the Owner or of persons supplying labor or materials in the prosecution of the work
contemplated by the Contract.
6. That the Contractor shall not commence any work to be perforted under this Contract until he has obtained from
responsible insurance companies, all insurance required, as set forth in the General Provisions and that the
Contractor shall maintain this insurance in full force and effect until the work to be performed under this Contract
has been accepted by the Owner.
7. That the Contractor shall not start working on any alterations requiring a supplemental agreement until the
agreement setting forth the adjusted price shall be executed by the Owner and the Contractor.
8. That the Contractor, at all times, shall observe and comply with all federal, state, territory or possession and local
laws, codes, ordinances and regulations in any manner affecting the conduct of the work, and the Contractor and
FAA All, 03-19-0094-048 (CARES MNT) Hangars 1 & 2 Roni Repairs
Contract Waterloo Regional Airport - 60675091
13. Second Party shall maintain all work done hereunder in good order for a period of 12 months from and after the
date it is accepted by the Waterloo Regional Airport, City of Waterloo, Iowa, which maintenance shall be without
expense to First Party or the abutting property. In the event of the failure or default of Second Party to remedy any
or all defects appearing in said work within a period of 12 months from the date of its acceptance by said Board
and after having been given ten (10) days' notice so to do by registered letter deposited in the United States Post
Office in said City, addressed to said Contractor at the address herein given, then First Party may proceed to
remedy such defects and the cost and expenses thereof may be recovered from said Second Party and the sureties
on its bond by action brought in any court of competent jurisdiction, but such suit may be brought in the District
Court of Black Hawk County, lowa.
IN WITNESS WHEREOF, the partiesreto have set their hands for the purpose herein expressed to this and three other
instruments of like tenor, as of the 3 day of )a.R. , 2023
CITY OF WATERLOO
Byf1
Mayor
CONTRACTOR
MODERN BUILDERS, INC.
BYA
etrsY✓r
S vi A%A-4,1/4-511 Po 842
A ,n job, ,/ /z Business Address
Witness
Finn Name
Signature
Title
FAA MP r13-19-0094.04S (CARES MNl) C-3 Hangars t & 2 Roof Repairs
Contract Waterloo Regional Airport - 60675091