HomeMy WebLinkAboutMunicipal Pipe Tool Co., CO#2 - Cont. No. 1063 - 6.5.2023AECOM
May 23, 2023
Mr. Jesse Gaherty
Waste Management Services
City of Waterloo
3505 Easton Avenue
Waterloo, Iowa, 50702
Subject: FY 2023 CIP Pipelining Phase IVA3
Change Order No. 2
City of Waterloo, Iowa
City Contract No. 1063
AECOM #60682318
Dear Mr. Gaherty:
Attached is Change Order No. 2 for the FY 2023 CIP Pipelining Phase IVA3.
AECOM
501 Sycamore Street
Suite 222
Waterloo, Iowa 50703
www.aecom.com
319-232-6531 tel
319-232-0271 fax
This change order is to add non-SRF work, as requested by City Staff, to make CIPP repairs in Service Area 13 on
Wyoming. Service Area 13 is not included in the Phase III SRF IUP and, therefore, cannot be included in any SRF
reimbursement. This work will be presented for payment separately from the SRF portion of this project.
These segments are on the verge of collapse and need to be repaired before they deteriorate further and require complete
replacement.
AECOM has reviewed the work described in this change order. We recommend that the City of Waterloo approve Change
Order No. 2 in the amount of $23,630.45 (non-SRF).
The final contract amount of $1,010,539.90 (SRF) and $33,812.45 (non-SRF) brings the total contract to $1,044,352.35.
That is a total increase to the contract of 2.34%.
Yours sincerely,
Christopher G. Oelkers, PE
Enclosure: Change Order No. 2 Tabulation and Signature Form
Municipal Pipe Tool Co. LLC Change Order No. 2 Estimate
L:\DCS\Projects\WTR\60682318_CIPP_Ph_IVA3\600_Construction_Support\660_Change_Orders\CO NO. 2 - NON SRF\Wat CIPP PH IVA - Change Order No 2 LTR.docx
CHANGE ORDER NO. 2
Owner City of Waterloo
Project FY 2023 CIP PIPELINING PHASE IVA3
Date: May 24, 2023
Owner's Contract No. 1063
Contractor: Municipal Pipe Tool Co. LLC
SRF NON-SRF
Date of Contact Start
6-J u 1-21
Contract Amount:
$ 1,010,539.90 $
You are directed to make the following changes in the Contract Documents. Description:
301
WYOMING
$ 23,630.45
TOTAL
$ 23,630.45
ADDITION
Reason for Change Order
QUANTITY RECONCILIATION - See the attached AECOM Change Order No. 1 Tabulation
CONTRACT PRICE
SRF
NON- SRF
Original:
$ 1,010,539.90
$ 1,010,539.90
$ -
Previous C.O.s (ADD/DEDUCT)
$ -
$ -
$ 10,182.00
This C.O. (ADD/DEDUCT)
$ 23,630.45
$ 23,630.45
Contract Price with all approved
$ 1,034,170.35
$ 1,010,539.90
$ 33,812.45
Total Change Orders:
$ 23,630.45
2.34% Total CO %
TOTAL
$ 1,044,352.35
Original Completion Date:
Revised Completion Date:
CONTRACT TIME
To Substantial
Completion
To Final
Completion
6/23/2023
12/31/2023
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPROVED:
BY: Qtteri ui J IN'E
$ICNEB
Owner (Authorized Signature)
ACCEPTED:
BY:
ZW14 WCAAGItA_A-6Uk-
6/5/2023
Date
May 24, 2023
Contractor (Authorized Signature) Date
ACCEPTED:
BY:
May 24, 2023
AECOM Date
AECOM
60682318 I 2
Project No. C.O. No.
MUNICIPAL
PIPE TOOLF
" We Protect the Environment"
Quoted to:
CITY OF WATERLOO
CITY CLERK
715 MULBERRY ST
WATERLOO, IA 50703
515 5TH STREET -- PO BOX 398
HUDSON, IOWA 50643
Phone: 319-988-4205
Fax: 319-988-3506
Quotation
Quote Number:
5404
Fax: 319-291-4571
Quote Date:
May 10, 2023
Page:
1
Customer ID
Good Thru
Payment Terms
Sales Rep
WATERLcity
6/9/23
Net 15 Days
Quantity
Description
Unit Price
Extension
3.00
1.00
365.00
365.00
365.00
1.00
1.00
1.00
CIPP Quote for Wyoming aggregate pipe with holes and roots.
TV, Clean, some root removal with 1ST robot - hourly
CIPP Crew Mobilization - Lump sum
CIPP line 8" Sanitary Sewer per linear foot
Pull tape installed on CIPP liner for this install to keep liner in pipe and
not travel up in holes. - LF
Preliner if needed for install - LF
Lateral Reinstatements - each (to be confirmed with the City before install)
Access, water and debris location provided by general/city close to
jobsite. We provide cones and work ahead signs only. Bonds not
included.
MPT will provide traffic cones and road work ahead signs only. Flaggers
575.00
3,750.00
32.50
10.50
6.33
150.00
1,725.00
3,750.00
11,862.50
3,832.50
2,310.45
150.00
If our equipment become lodged during attempts to perform duties specified by
customer, all costs for removal and replacement of equipment will be the customers.
Quantities shown are estimated and not guaranteed; they are solely for establishing
the initial unit price for the services listed above. Final charges will be based on
actual quantities.
Subtotal
Sales Tax
Freight
Continued
Continued
Total Continued
ACCEPTED BY: Signature Title Date
Scheduling Contact Person: Phone #: Cell
MUNICIPAL
PIPE TOOLF
WWW.MUNIPIPE,COM
"We Protect the Environment"
Quoted to:
CITY OF WATERLOO
CITY CLERK
715 MULBERRY ST
WATERLOO, IA 50703
515 5TH STREET — PO BOX 398
HUDSON, IOWA 50643
Phone: 319-988-4205
Fax: 319-988-3506
Fax:
Quotation
Quote Number:
5404
319-291-4571
Quote Date:
May 10, 2023
Page:
2
Customer ID
Good Thru
Payment Terms
Sales Rep
WATERLcity
6/9/23
Net 15 Days
Quantity
Description
Unit Price
Extension
and other traffic control provided by General.
RR ROW insurance, flaggers and permit are not included. If they are
needed, please send information on railroad and contact person so we
can quote it.
If our equipment become lodged during attempts to perform duties specified by
customer, all costs for removal and replacement of equipment will be the customers.
Quantities shown are estimated and not guaranteed; they are solely for establishing
the initial unit price for the services listed above. Final charges will be based on
actual quantities.
Subtotal
Sales Tax
Freight
Total
ACCEPTED BY: Signature Title Date
23, 630.45
23, 630.45
Scheduling Contact Person:
Phone #: Cell