HomeMy WebLinkAboutD&N Fence - CO#1 FY24 Trolley Car Trail Project No. 1093 - 11.6.2023CITY OF WATERLOO, IOWA
CHANGE OR EXTRA WORK ORDER NO. 01
PROJECT: FY 2024 TROLLEY CAR TRAIL CHAIN LINK FENCE REPLACEMENT, CONTRACT NO. 1093
DATE PREPARED: OCTOBER 20, 2023 AMOUNT: $64,650 INCREASE
TO: D & N FENCE , CONTRACTOR
YOU ARE HEREBY ORDERED TO MAKE THE FOLLOWING CHANGES FROM THE PLANS AND SPECIFICATIONS OR PERFORM THE
FOLLOWING EXTRA WORK ON YOUR CONTRACT DATED NOVEMBER 6, 2023.
A. DESCRIPTION OF CHANGE TO BE MADE OR EXTRA WORK TO BE DONE:
INCREASE REPAIR QUANTITIES FOR PROJECT ITEMS.
B. REASON FOR ORDERING CHANGE OR EXTRA WORK:
AVAILABILITY OF ADDITIONAL FUNDS HAS ALLOWED FOR THE REMOVAL AND REPLACEMENT OF ENTIRE FENCING
ALONG TROLLEY TRAIL INSTEAD OF HAVING TWO SEPARATE CONTRACTS.
C. SETTLEMENT FOR COST OF WORK TO BE MADE AS FOLLOWS:
ITEM
DESCRIPTION
UNIT
EST QTY
UNIT PRICE
TOTAL PRICE
1
REMOVAL OF FENCE, 3'-10" HIGH
LE
1400
$ 6.00
$ 8,400.00
2
INSTALLATION OF FENCE, 4'-0" HIGH
LF
1400
$ 38.75
$ 48,650.00
3
TRAFFIC CONTROL
LS
1
$ -
$ -
4
MOBILIZATION
LS
1
$ 2,000.00
$ 2,000.00
BY: 62uerz- uz 9(LV
MAYOR
ATTEST:
f11GIiALLP 11/6/2023
SIGNED
Re[fey Tefch[e
SIGNED
DATE
TOTAL INCREASE = $ 64,650.00